The Cheyenne Frontier Days Park-N-Ride and I-25 Pedestrian Bridge Project
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
05/29/2026
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Highway Administration
Other Agencies with Actions or Authorizations:
Department of Defense, US Air Force
Description:
The Cheyenne Frontier Days Park-N-Ride and Interstate 25 (I-25) Pedestrian Bridge Project proposes construction of a 36.5-acre overflow parking facility on the eastern edge of Francis E. Warren Air Force Base (FEW) and a new pedestrian bridge crossing I-25 to connect the Park N Ride to the Cheyenne Frontier Days (CFD) event grounds. The project will improve traffic management and pedestrian safety during large-scale events by providing dedicated off-site parking and grade-separated pedestrian access between the parking area west of I-25 and the CFD venue east of I-25. WYDOT and FHWA will authorize right-of-way access for bridge construction; FEW will issue a right-of-entry and temporary use license for the parking facility.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|