Charlotte Transit Center Redevelopment

PROJECT WEBSITE: https://www.charlottenc.gov/CATS/Events/Virtual-Public-Meeting-for-CTC-Redevelo…

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Class of Action Changed

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
CLASS OF ACTION CHANGED

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
N/A

1 out of 1

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Transit Administration

Description:

The Charlotte Area Transit System (CATS) and City of Charlotte (City) are proposing to construct the Charlotte Transit Center Redevelopment Project located at 310 E. Trade Street in Charlotte, NC. The project would demolish the existing Charlotte Transportation Center (CTC) and construct a new modernized multimodal facility to connect Charlotte’s downtown core to the Charlotte metropolitan area. CATS/City, in partnership with WPTP Brevard Holdings LLC, is proposing a joint development project to construct the new multimodal facility along with high-density mixed-use development known as the Charlotte Multimodal Transit Hub. Phase I of the project would construct a temporary bus transit facility across and southwest of the existing CTC facility, along with a connector road. Phase II of the project would demolish the existing CTC facility and construct a permanent multimodal facility on the current CTC site.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete