Carteret Ferry Terminal

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
09/25/2024

2 out of 2

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Transit Administration

Description:

The Borough of Carteret, NJ seeks to construct a ferry terminal that would facilitate commuter ferry service between the Borough of Carteret and New York City. The proposed ferry terminal would be constructed on the waterfront of the Arthur Kill tidal strait approximately 45 minutes south of Manhattan, in Middlesex County, NJ. The project includes construction of a five-story, 62,500 square foot terminal building, floating docks with capability to accommodate two 149 passenger vessels, and ancillary site improvements, such as sidewalks, parking, lighting, landscaping. The Borough believes implementation of commuter ferry service will catalyze economic development and provide a high-quality transit option for its residents.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete