Carolina Bays Parkway Extension
PROJECT WEBSITE: https://www.ncdot.gov/projects/carolina-bays-parkway/Pages/default.aspx
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
04/30/2027
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Highway Administration
Other Agencies with Actions or Authorizations:
Department of the Army, US Army Corps of Engineers - Regulatory
Department of the Interior, Fish and Wildlife Service
Description:
The N.C. Department of Transportation and the S.C. Department of Transportation are planning to extend Carolina Bays Parkway (S.C. 31) from S.C. 9 in Horry County, South Carolina, across the North Carolina state line to U.S. 17 in Brunswick County.
The project is expected to involve the construction of a multi-lane expressway and might involve existing roadways and areas on new locations. The primary purpose of the project is to improve the transportation network in the study area by enhancing traffic flow and connectivity for traffic moving in and through the area.
The extension would provide a more direct and efficient movement of traffic seeking to bypass congestion within the areas of Calabash in North Carolina as well as Little River and the Grand Strand areas in South Carolina. As a result, local and tourist traffic on area roadways would experience less congestion and delays.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|