Cape Cod Bridges Program

PROJECT WEBSITE: https://www.mass.gov/cape-bridges

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
09/11/2026

12 out of 12

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Highway Administration

Other Agencies with Actions or Authorizations:

Department of the Army

Department of the Army, US Army Corps of Engineers - Civil Works

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Department of Homeland Security

Department of Homeland Security, US Coast Guard

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

No icon

States

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Description:

Constructed in 1935, the Sagamore and Bourne National Highway System (NHS) bridges cross the Federal Cape Cod Canal, providing the only vehicular access for 15 towns, 215,000 year-round residents, and more than 35 million vehicles that cross Cape Cod Canal each year. Both bridges, which are owned and maintained by the U.S. Army Corps of Engineers (USACE), are in poor condition and do not meet present and future transportation requirements. The Cape Cod Bridges Program (CCBP) proposes critical transportation infrastructure improvements including replacement of the Bourne and Sagamore highway bridges spanning Cape Cod Canal; reconfiguration of the highway approach networks north and south of Cape Cod Canal to align with the replacement highway bridges; and provision of separated pedestrian and bicycle accommodations along the replacement bridges with connections to the local roadway network.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete