Buffalo-Amherst-Tonawanda Corridor Transit Expansion EIS

PROJECT WEBSITE: https://www.nftametrotransitexpansion.com/

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
02/20/2026

2 out of 2

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Transit Administration

Description:

The proposed Buffalo-Amherst-Tonawanda Corridor Transit Expansion Project is a proposed approximately seven-mile expansion of high-quality transit service to Buffalo, New York to Tonawanda and Amherst, New York.  The alternatives being considered include a light rail transit extension, a bus rapid transit system, and the no-build alternative.  Both build alternatives would follow essentially the same alignment and would be primarily at-grade. Ten stations, two with park & ride facilities and an overnight storage and light maintenance facility are proposed for both build alternatives.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete