Buck O'Neil
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
05/15/2020
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Highway Administration
Description:
Improve the transportation infrastructure at the US-169 crossing of the Missouri River in Kansas City
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|