Bruckner Expwy - Hutchinson Pkwy Mobility Improvement Project, Bronx Co., NYC
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
08/05/2021
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Highway Administration
Description:
The Build Alternative reconfigures the I-95/Pelham Parkway Interchange, extends the I-95 northbound fourth travel lane to exit to the Hutchinson River Parkway, constructs a new exit ramp from northbound Hutchinson River Parkway to Bartow Avenue, and reconfigures and improves the operation and safety of the pedestrian/bicyclist paths within the I-95/Pelham Parkway Interchange, Pelham Bay Park in the vicinity of the interchange, and along Bartow Avenue near the Hutchinson River Parkway. This alternative will improve traffic flow, vehicular and pedestrian/bicyclist safety along the northbound I-95 ramps, improve geometric and operational deficiencies associated with the I-95 ramps, and provide direct access to Co-op City, thereby satisfying the Project purpose and objectives.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|