Broward Commuter Rail South Project
PROJECT WEBSITE: https://www.fdot.gov/projects/broward-commuter-rail-south/home
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
09/05/2024
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Transit Administration
Description:
Broward County proposes to implement commuter rail service along 11.5 miles of the existing Florida East Coast (FEC) Railway from the Brightline Aventura Station in Miami-Dade County to the Broward Health Medical Center in Fort Lauderdale. The proposed project includes three stations and parking facilities that are expected to be built within existing city, county, and/or FEC Railway properties along with corresponding improvements to the existing Hialeah Maintenance Facility in Miami-Dade County. Other elements include track, signaling, and safety and communication improvements along the corridor, as well as acquisition of rolling stock for the service. According to Broward County, the project plans to share the FEC Railway with freight trains and intercity passenger trains.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|