Brooks Bridge Replacement Study
PROJECT WEBSITE: Brooks Bridge Replacement Study
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
09/26/2023
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Florida
Description:
The proposed project involves replacement of the John T. Brooks Bridge (Bridge Number 570034) which carries S.R. 30 (U.S. 98) over the Santa Rosa Sound which includes the GIWW in Okaloosa County. To accommodate the bridge replacement, intersection improvements are necessary at S.R. 145 (Perry Avenue) on the west end of the bridge in the City of Fort Walton Beach, and in the vicinity of Santa Rosa Boulevard, extending to Pier Road on the east end on Okaloosa Island.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|