Brent Spence Bridge Corridor Project

PROJECT WEBSITE: https://brentspencebridgecorridor.com/

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
04/27/2026

6 out of 6

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Highway Administration

Description:

The Brent Spence Bridge (BSB) corridor consists of 7.8 total miles of I-71 and I-75 located within portions of Ohio and Kentucky. The project corridor primarily utilizes the existing I-71/I-75 alignment from the southern project limits at Dixie Highway and to the north to Kyles Lane.

This corridor is located within the Greater Cincinnati/Northern Kentucky region and is a major route for regional and local mobility.  Regionally, the BSB carries both I-71 and I-75 traffic over the Ohio River and connects to I-74, I-275, and US-50. The corridor is also one of the busiest trucking routes in the United States, connecting Michigan to Florida via I-75. The BSB corridor also facilitates local travel by providing access to downtown Cincinnati in Hamilton County, Ohio and Covington in Kenton County, Kentucky. 

Safety, congestion, and geometric problems exist on the structure and its approaches.  The Brent Spence Bridge, which opened to traffic in 1963, was designed to carry 80,000 vehicles per day.  Currently, approximately 160,000 vehicles per day use the Brent Spence Bridge and traffic volumes are projected to increase to approximately 233,000 vehicles per day in 2035.
 

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete