Better Market Street
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
09/11/2020
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
California, CalTrans
Description:
San Francisco Public Works (Public Works), in coordination with the Citywide Planning Division of
the San Francisco Planning Department, the San Francisco Municipal Transportation Agency
(SFMTA), the San Francisco Public Utilities Commission (SFPUC), and the San Francisco County
Transportation Authority (SFCTA), proposes to make Market Street safer and more efficient for all
modes of transportation by reducing conflicts between transit, paratransit, taxis, commercial
vehicles, cyclists, and pedestrians. The following sections describe the project location, purpose and
need, independent utility and logical termini, existing conditions, Build Alternative, No-Build
Alternative, and the needed permits and approvals.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|