Avenue E: SR 195 to County 18th Street

PROJECT WEBSITE: Yuma County Public Project Description

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
07/30/2021

2 out of 2

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Arizona

LEAD AGENCY
Arizona

Description:

The Arizona Department of Transportation (ADOT), in collaboration with Yuma County is planning a roadway construction project that would provide an approximate 5.60-mile-long connection between SR 195 and County 18th Street within and adjacent to the city of San Luis, Yuma County, Arizona. The project begins at the Avenue E and SR 195 intersection, traveling northeast and passing to the east of Rolle Airfield, and then extending north to tie into to the existing Avenue D roadway approximately 0.20 mile north of County 18th Street.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete