USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Portions of this site may be affected due to a lapse in appropriations and associated shutdown/furloughs. Please monitor this page for updates on site availability and operating status.

Arkadelphia Bypass

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
08/18/2021

1 out of 1

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Highway Administration

Description:

2 lane bypass on new location from Hwy 67 - Hwy 51 

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete