Aberdeen Carolina and Western Railway Congestion Mitigation Project
PROJECT WEBSITE: Aberdeen Carolina and Western Railway Congestion Mitigation Project
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
09/30/2022
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Railroad Administration
Description:
Aberdeen Carolina and Western Railway (ACWR) is proposing to use Federal Railroad Administration (FRA) Consolidated Rail Infrastructure and Safety Improvements (CRISI) Program funding and Railroad Rehabilitation and Improvement Funding (RRIF) to administer a congestion mitigation project (the Proposed Action). The Proposed Action includes the construction of five new facilities:
- three storage and passing sidings,
- two storage and switching yards, and
- one warehouse.
The purpose of the Proposed Action is to address congestion issues on the existing railroad. All construction activities would take place within the existing ACWR railroad right-of-way (ROW) or on land owned by an ACWR.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|