9TH AVE INTERCHANGE IN HANFORD
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
							ENVIRONMENTAL REVIEW AND PERMITTING STATUS
							IN PROGRESS
						
																																				ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
																																07/31/2027
																					
							ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
							COMPLETED
						
								SECTOR
								Surface Transportation
							
							CATEGORY
																						
								Project Category
              DOT Projects
																				
								LEAD AGENCY
																	California, CalTrans
															
Description:
**LOCAL OVERSIGHT** NEPA
The project proposes to upgrade a 1.4-mile section of the State Route (SR) 198 expressway in Hanford to a freeway by eliminating the at-grade intersection at 9th Avenue and constructing an interchange.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
 
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
 - Responsible Agency:
 - Bureau:
 - Action Status:
 - SHPO:
 - Action Identifier:
 - Action Outcome:
 
| Milestone | Original Target Date | Current Target Date | Milestone Complete | 
|---|