605/Valley Blvd: Interchange Improvement Project
PROJECT WEBSITE: https://www.metro.net/projects/i-605-corridor-improvement-project/#documents
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
04/07/2021
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
California, CalTrans
Description:
The California Department of Transportation (Caltrans), in cooperation with Los Angeles County Metropolitan Transportation Authority (LA Metro), San Gabriel Valley Council of Governments (SGVCOG), Gateway Cities Council of Governments (GCCOG), Los Angeles County Department of Public Works (LACDPW), and City of Industry propose to improve mobility and relieve congestion, capacity constraints, and other related deficiencies on Interstate 605 (I-605) at the Valley Boulevard interchange. The I 605/Valley Boulevard Interchange Improvements Project (project) is an Early Action Project (EAP) of the I-605 Corridor Improvement Project and is located approximately two miles north of State Route 60 (SR-60) and a half-mile south of Interstate 10 (I-10) within portions of the City of Industry and unincorporated Los Angeles County.
Project improvements would occur at the I-605 and Valley Boulevard interchange between post miles R19.2 and R19.5, and include improvements to Valley Boulevard, Temple Avenue, the southbound (SB) loop off-ramp and northbound (NB) off-ramp onto Valley Boulevard, and the SB on-ramp, northbound (NB) loop on-ramp, and NB on-ramp from Valley Boulevard onto I-605. The new configuration and improvements would improve ramp queueing, capacity, and enhance motorist, bicycle, and pedestrian safety.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|