1121000214 - I-5/Harbor Drive Connected Corridor
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
01/25/2024
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
California, CalTrans
Description:
The Harbor Drive Corridor is a critical urban freight corridor serving as regional, state, and federal Port of Entry (POE) for San Diego’s “Working Waterfront.” Harbor Drive is a major four-lane roadway running the length of the Corridor and connecting the Working Waterfront to regional freeways Interstate 5 (I-5) and State Route 15 (SR-15) via arterials Cesar Chavez Pkwy, 28th St, 32nd St, 8th St and Civic Center Dr. The Corridor is home to the Port of San Diego’s Tenth Avenue and National City Marine Terminals, Naval Base San Diego (NBSD), several large commercial shipyards (“Shipyards”), industrial facilities, historic cultural and recreational sites, and AB-617 identified Portside Environmental Justice (EJ) Neighborhoods of San Diego’s Barrio Logan and National City. The proposed Harbor Drive 2.0 project would construct dedicated truck lanes and Intelligent Transportation Systems (ITS) technologies along Harbor Drive and arterial connections to I-5 and SR-15 in the cities of San Diego and National City. Additional improvements include installing upgraded and new traffic signals, freight signal priority and truck queue jumps, wayfinding gantries and installing upgraded electrical equipment. and other supportive infrastructure. Construction of electrical connections to support the deployment of alternative fuel and zero-emission vehicle charging and other pilot innovations. Construct ADA curbs and adding crosswalks.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|