0720000152 - LA-110, Upgrade Bridge Railing, Construct retaining wall
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
06/19/2025
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
California, CalTrans
Description:
Purpose and Need The purpose of the proposed project is to address the deficiencies and non-standard features at the northbound State Route 110 (SR-110) and Interstate 5 (I-5) Connecter Sidehill Viaduct (Bridge No. 53-2225G) in Los Angeles County. This project is the retaining wall portion in support of the bridge rail upgrade project.
Description of work The current scope of the project requires a retaining wall to be constructed to support the shoulder widening and the new concrete barrier of the Bridge Rail Upgrade project (07-36930). The existing overhead sign structures need to be upgraded to meet the new wind load standards. The overhead sign panels will also need to be upgraded to the current retroreflective sign standards. Additional work includes upgrading the crash cushion, highway safety lighting, roadway signs and installing rumble strips along the shoulder.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|