USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 08-04-2023 09-01-2023 09-29-2023 Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 10-18-2023 11-17-2023 01-10-2024 Yes
ESA Consultation Concludes (Agency Action) 02-14-2024 03-08-2024 05-31-2024 Yes
In Progress
There has been a schedule shift in the EDD request.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 08-04-2023 09-01-2023 09-29-2023 Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 10-18-2023 11-17-2023 01-10-2024 Yes
ESA Consultation Concludes (Agency Action) 02-14-2024 03-08-2024 05-31-2024 No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 08-04-2023 09-01-2023 09-29-2023 Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 10-18-2023 11-17-2023 01-10-2024 Yes
ESA Consultation Concludes (Agency Action) 02-14-2024 03-08-2024 05-15-2024 No
Planned
FWS is waiting for additional information from BOEM and the project sponsor.  
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 08-04-2023 09-01-2023 09-29-2023 Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 10-18-2023 11-17-2023 01-19-2024 No
ESA Consultation Concludes (Agency Action) 02-14-2024 03-08-2024 05-15-2024 No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 08-04-2023 09-01-2023 09-29-2023 Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 10-18-2023 11-17-2023 12-22-2023 No
ESA Consultation Concludes (Agency Action) 02-14-2024 03-08-2024 04-12-2024 No
Planned
Additional information required of, and provided by, the Project Sponsor resulted in a delay of slightly more than one month in the development of the DEIS.  FWS anticipates a delay of about one month due to the delay in receipt of the ESA consultation request resulting from changes to the project activities. This delay has cascading delays on subsequent ESA milestones.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 08-04-2023 09-01-2023 10-06-2023 No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 10-18-2023 11-17-2023 12-22-2023 No
ESA Consultation Concludes (Agency Action) 02-14-2024 03-08-2024 04-12-2024 No
Planned
The timing of the ESA consultation milestones relates to the NEPA schedule. Because BOEM extended the NEPA milestones by 28 days, this milestone is being moved accordingly. The reason the NEPA timeline changed was to allow the project sponsor to clarify their submissions related to consultations with NMFS, to allow time to address inconsistencies and outstanding questions.   
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 08-04-2023 09-01-2023 --- No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 10-18-2023 11-17-2023 --- No
ESA Consultation Concludes (Agency Action) 02-14-2024 03-08-2024 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) --- 08-04-2023 --- No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) --- 10-18-2023 --- No
ESA Consultation Concludes (Agency Action) --- 02-14-2024 --- No