Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 06-30-2023 09-01-2023 --- Yes
Completeness Determination (Agency Action) 07-28-2023 09-08-2023 --- Yes
Complete application submitted (Applicant Action) 09-28-2023 11-24-2023 --- Yes
Issuance of Decision (Agency Action) 09-24-2024 01-03-2025 --- Yes
In Progress
A commensurate extension of the Section 10/404/408 final completion date is requested based upon the extension of the ROD milestone. Factors that inform the USACE final decision include the conclusion of Delaware Natural Resources and Environmental Control's (DNREC) Section 401 water quality certification (WQC) process. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 06-30-2023 09-01-2023 --- Yes
Completeness Determination (Agency Action) 07-28-2023 09-08-2023 --- Yes
Complete application submitted (Applicant Action) 09-28-2023 11-24-2023 --- Yes
Issuance of Decision (Agency Action) 09-24-2024 01-03-2025 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 06-30-2023 09-01-2023 --- Yes
Completeness Determination (Agency Action) 07-28-2023 09-08-2023 --- Yes
Complete application submitted (Applicant Action) 09-28-2023 11-24-2023 --- Yes
Issuance of Decision (Agency Action) 09-24-2024 11-29-2024 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 06-30-2023 09-01-2023 --- Yes
Completeness Determination (Agency Action) 07-28-2023 09-08-2023 --- Yes
Complete application submitted (Applicant Action) 09-28-2023 11-28-2023 --- Yes
Issuance of Decision (Agency Action) 09-24-2024 11-29-2024 --- No
In Progress
Application was submitted on 1 Sept 2023, a couple of days after the milestone date of 30 Aug 2023. The USACE Philadelphia District evaluated the application for completeness and determined that the application was not complete; the milestone was completed earlier than scheduled. Missing documentation was identified and communicated to the applicant.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 06-30-2023 09-01-2023 --- Yes
Completeness Determination (Agency Action) 07-28-2023 09-08-2023 --- Yes
Complete application submitted (Applicant Action) 09-28-2023 11-28-2023 --- No
Issuance of Decision (Agency Action) 09-24-2024 11-29-2024 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 06-30-2023 08-30-2023 --- Yes
Completeness Determination (Agency Action) 07-28-2023 09-29-2023 --- No
Complete application submitted (Applicant Action) 09-28-2023 11-28-2023 --- No
Issuance of Decision (Agency Action) 09-24-2024 11-29-2024 --- No
Planned
Additional information required of, and provided by, the Project Sponsor results in a delay of slightly more than one month in the development of the DEIS, and cascading delays in the FEIS and ROD. BOEM prepared a draft EIS based on the COP updates available in November 2022 and completed a cooperating agency review of the partial DEIS in June 2023. The Project Sponsor submitted a COP update in Nov 2022 and an additional COP update in July 2023. BOEM cannot complete the DEIS until all the Project Sponsor’s complete revisions to the PDE and associated reports have been provided, reviewed, and incorporated into the analysis in the DEIS. The PDE changes in the COP update include additional dredging, updated cable routes, and refinement of O&M facility details.  This additional information is required for the DEIS, which will shift the date for the ROD.  Since the Section 408 final milestone is dependent upon the ROD, the final Section 408 milestone is shifting accordingly. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 06-30-2023 08-30-2023 --- No
Completeness Determination (Agency Action) 07-28-2023 09-29-2023 --- No
Complete application submitted (Applicant Action) 09-28-2023 11-28-2023 --- No
Issuance of Decision (Agency Action) 09-24-2024 11-29-2024 --- No
Planned
Applicant has indicated that they will be delayed in submitting their Section 408 application. There was a prior applicant delay to July 26, 2023, which has been extended an additional month to Aug 30, 2023. The interim milestones were updated to reflect the changes. The USACE District Project Manager has coordinated the revised application submittal date with the applicant and the applicant has agreed to the revised interim milestones.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 06-30-2023 08-30-2023 --- No
Completeness Determination (Agency Action) 07-28-2023 09-29-2023 --- No
Complete application submitted (Applicant Action) 09-28-2023 11-28-2023 --- No
Issuance of Decision (Agency Action) 09-24-2024 10-24-2024 --- No
Planned
The schedule has been updated in accordance with BOEM's revised EIS schedule. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 06-30-2023 07-26-2023 --- No
Completeness Determination (Agency Action) 07-28-2023 08-25-2023 --- No
Complete application submitted (Applicant Action) 09-28-2023 10-25-2023 --- No
Issuance of Decision (Agency Action) 09-24-2024 10-24-2024 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 06-30-2023 06-30-2023 --- No
Completeness Determination (Agency Action) 07-28-2023 07-28-2023 --- No
Complete application submitted (Applicant Action) 09-28-2023 09-28-2023 --- No
Issuance of Decision (Agency Action) 09-24-2024 09-24-2024 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) --- 06-30-2023 --- No
Completeness Determination (Agency Action) --- 07-28-2023 --- No
Issuance of Decision (Agency Action) --- 09-24-2024 --- No