Permitting Action Modification History
Modifications on 08/17/2023
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) | 08-01-2027 | 08-01-2027 | --- | No |
| Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) | 11-01-2027 | 11-01-2027 | --- | No |
| Final Verification/Permit Decision Rendered (Agency Action) | 06-01-2028 | 06-01-2028 | --- | No |
Modifications on 09/20/2022
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) | --- | 08-01-2027 | --- | No |
| Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) | --- | 11-01-2027 | --- | No |
| Final Verification/Permit Decision Rendered (Agency Action) | --- | 06-01-2028 | --- | No |
Modifications on 02/28/2022
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) | --- | 08-01-2027 | --- | No |
| Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) | --- | 11-01-2027 | --- | No |
| Final Verification/Permit Decision Rendered (Agency Action) | --- | 06-01-2028 | --- | No |