Permitting Action Modification History

Complete
Section 106 consultation has been completed. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 11-08-2021 11-08-2021 --- Yes
Section 106 consultation concluded (Agency Action) 08-30-2022 11-30-2022 --- Yes
In Progress
The Programmatic Agreement (PA) will need to be revised, based on the new routes changes in New Mexico. TBLM's Section 106 Project Lead feels we should allow more time for all this to be conducted and not be held to a tight timeframe. The Project Sponsor has been consulted on the proposed change to the Sec.106 Consultation Fast-41 milestone date and has no issues with and supports the milestone change.   Executive Director Determination was signed on 7/28/2022 granting the date change. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 11-08-2021 11-08-2021 --- Yes
Section 106 consultation concluded (Agency Action) 08-30-2022 11-30-2022 --- No