Permitting Action Modification History
Modifications on 08/17/2023
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) | 01-01-2027 | 01-01-2027 | --- | No |
| Scoping (Agency Action) | 01-01-2027 | 01-01-2027 | --- | No |
| Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) | 08-01-2027 | 08-01-2027 | --- | No |
| Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) | 04-01-2028 | 04-01-2028 | --- | No |
| Issuance of Lead Agency Record of Decision (Agency Action) | 08-01-2028 | 08-01-2028 | --- | No |
Modifications on 09/20/2022
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) | --- | 01-01-2027 | --- | No |
| Scoping (Agency Action) | --- | 01-01-2027 | --- | No |
| Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) | --- | 08-01-2027 | --- | No |
| Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) | --- | 04-01-2028 | --- | No |
| Issuance of Lead Agency Record of Decision (Agency Action) | --- | 08-01-2028 | --- | No |