USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

In Progress
On February 11th, EDFR (Project Sponsor) presented a revised site plan that combines elements studied in the Draft EIS to create a project that has fewer environmental impacts. EDFR understands that it will take time to review this revised plan in detail, even though it combines various elements that have already been studied. EDFR has requested extensions of time to allow for the Applicant and the Agencies to coordinate on the incorporation of the revisions and to develop commensurate and appropriate mitigation measures to reflect the reduced impacts of the project. The time will also allow BLM and FWS to incorporate these recent design revisions provided by the Applicant, along with commensurate prudent and reasonable measures, into the Biological Opinion. Subsequently these revisions would be reflected in the Final EIS for the Project.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 12-04-2020 12-04-2020 --- Yes
Completed application received (Agency Action) 10-07-2024 12-31-2023 --- Yes
Final decision/agency action (Agency Action) 01-07-2026 01-07-2026 --- No
In Progress
Interagency Factors
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 12-04-2020 12-04-2020 --- Yes
Completed application received (Agency Action) 10-07-2024 12-31-2023 --- Yes
Final decision/agency action (Agency Action) 01-07-2026 10-15-2025 --- No
In Progress
Complete application received ahead of scheduled milestone date.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 12-04-2020 12-04-2020 --- Yes
Completed application received (Agency Action) 10-07-2024 12-31-2023 --- Yes
Final decision/agency action (Agency Action) 01-07-2026 01-07-2026 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 12-04-2020 12-04-2020 --- Yes
Completed application received (Agency Action) 10-07-2024 10-07-2024 --- No
Final decision/agency action (Agency Action) 01-07-2026 01-07-2026 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 12-04-2020 12-04-2020 --- Yes
Completed application received (Agency Action) 10-07-2024 10-07-2024 --- No
Final decision/agency action (Agency Action) 01-07-2026 01-07-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 12-04-2020 12-04-2020 --- Yes
Completed application received (Agency Action) 10-07-2024 10-07-2024 --- No
Final decision/agency action (Agency Action) 01-07-2026 01-07-2026 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 12-04-2020 12-04-2020 --- Yes
Completed application received (Agency Action) 10-07-2024 10-07-2024 --- No
Final decision/agency action (Agency Action) 01-07-2026 01-07-2026 --- No