Permitting Action Modification History

In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 12-04-2020 12-04-2020 --- Yes
Completed application received (Agency Action) 10-07-2024 12-31-2023 --- Yes
Final decision/agency action (Agency Action) 01-07-2026 01-07-2026 12-19-2026 No
In Progress
Completion of the ROW is dependent upon the decisions made in the EIS Decision Record. The timing of this milestone has been adjusted to coincide with the changes made to the EIS milestones. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 12-04-2020 12-04-2020 --- Yes
Completed application received (Agency Action) 10-07-2024 12-31-2023 --- Yes
Final decision/agency action (Agency Action) 01-07-2026 01-07-2026 07-07-2028 No
In Progress
On February 11th, EDFR (Project Sponsor) presented a revised site plan that combines elements studied in the Draft EIS to create a project that has fewer environmental impacts. EDFR understands that it will take time to review this revised plan in detail, even though it combines various elements that have already been studied. EDFR has requested extensions of time to allow for the Applicant and the Agencies to coordinate on the incorporation of the revisions and to develop commensurate and appropriate mitigation measures to reflect the reduced impacts of the project. The time will also allow BLM and FWS to incorporate these recent design revisions provided by the Applicant, along with commensurate prudent and reasonable measures, into the Biological Opinion. Subsequently these revisions would be reflected in the Final EIS for the Project. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 12-04-2020 12-04-2020 --- Yes
Completed application received (Agency Action) 10-07-2024 12-31-2023 --- Yes
Final decision/agency action (Agency Action) 01-07-2026 01-07-2026 --- No
In Progress
Interagency Factors , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 12-04-2020 12-04-2020 --- Yes
Completed application received (Agency Action) 10-07-2024 12-31-2023 --- Yes
Final decision/agency action (Agency Action) 01-07-2026 10-15-2025 --- No
In Progress
Complete application received ahead of scheduled milestone date. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 12-04-2020 12-04-2020 --- Yes
Completed application received (Agency Action) 10-07-2024 12-31-2023 --- Yes
Final decision/agency action (Agency Action) 01-07-2026 01-07-2026 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 12-04-2020 12-04-2020 --- Yes
Completed application received (Agency Action) 10-07-2024 10-07-2024 --- No
Final decision/agency action (Agency Action) 01-07-2026 01-07-2026 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 12-04-2020 12-04-2020 --- Yes
Completed application received (Agency Action) 10-07-2024 10-07-2024 --- No
Final decision/agency action (Agency Action) 01-07-2026 01-07-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 12-04-2020 12-04-2020 --- Yes
Completed application received (Agency Action) 10-07-2024 10-07-2024 --- No
Final decision/agency action (Agency Action) 01-07-2026 01-07-2026 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 12-04-2020 12-04-2020 --- Yes
Completed application received (Agency Action) 10-07-2024 10-07-2024 --- No
Final decision/agency action (Agency Action) 01-07-2026 01-07-2026 --- No