Permitting Action Modification History

Cancelled
Action is cancelled, due to determination by USACE that a Section 408 is not required for this proposed project. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 11-30-2022 12-28-2022 --- No
Completeness Determination (Agency Action) 12-30-2022 01-27-2023 --- No
Complete application submitted (Applicant Action) 03-28-2023 03-28-2023 --- No
Issuance of Decision (Agency Action) 01-25-2024 01-25-2024 --- No
Planned
Moved from Needs Review back to Draft state while USACE reviews date change proposals. Original Target Date Entry Effort Updated to reflect delay caused by finalization of alternatives. Third milestone was not updated yet because it would go past 30 days of the final date on this action.   , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 11-30-2022 12-28-2022 --- No
Completeness Determination (Agency Action) 12-30-2022 01-27-2023 --- No
Complete application submitted (Applicant Action) 03-28-2023 03-28-2023 --- No
Issuance of Decision (Agency Action) 01-25-2024 01-25-2024 --- No