USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

Complete
Ahead of scheduled April 2024 date
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 03-10-2022 03-10-2022 --- Yes
OCS Air Permit application submitted (Applicant Action) 06-10-2022 08-10-2022 --- Yes
OCS Air Permit application complete (Applicant Action) 09-09-2022 04-20-2023 --- Yes
Issuance of final decision/permit approval (Agency Action) 09-08-2023 02-15-2024 --- Yes
Complete
milestone completed earlier, on Feb 15, prior to the April 22 milestone date.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 03-10-2022 03-10-2022 --- Yes
OCS Air Permit application submitted (Applicant Action) 06-10-2022 08-10-2022 --- Yes
OCS Air Permit application complete (Applicant Action) 09-09-2022 04-20-2023 --- Yes
Issuance of final decision/permit approval (Agency Action) 09-08-2023 04-15-2024 --- Yes
In Progress
EPA deemed the Project Sponsor’s OCS air permit application complete on April 20, 2023.  Accordingly, the requested final completion date for the OCS air permit action is April 22, 2024 (due to weekend).
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 03-10-2022 03-10-2022 --- Yes
OCS Air Permit application submitted (Applicant Action) 06-10-2022 08-10-2022 --- Yes
OCS Air Permit application complete (Applicant Action) 09-09-2022 04-20-2023 --- Yes
Issuance of final decision/permit approval (Agency Action) 09-08-2023 04-22-2024 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 03-10-2022 03-10-2022 --- Yes
OCS Air Permit application submitted (Applicant Action) 06-10-2022 08-10-2022 --- Yes
OCS Air Permit application complete (Applicant Action) 09-09-2022 04-20-2023 --- Yes
Issuance of final decision/permit approval (Agency Action) 09-08-2023 01-22-2024 --- No
Planned
Sponsor delays in complete application submission
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 03-10-2022 03-10-2022 --- Yes
OCS Air Permit application submitted (Applicant Action) 06-10-2022 08-10-2022 --- Yes
OCS Air Permit application complete (Applicant Action) 09-09-2022 05-04-2023 --- No
Issuance of final decision/permit approval (Agency Action) 09-08-2023 01-22-2024 --- No
Planned
Sponsor delays in complete application submission
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 03-10-2022 03-10-2022 --- Yes
OCS Air Permit application submitted (Applicant Action) 06-10-2022 08-10-2022 --- Yes
OCS Air Permit application complete (Applicant Action) 09-09-2022 03-03-2023 --- No
Issuance of final decision/permit approval (Agency Action) 09-08-2023 01-22-2024 --- No
Planned
Sponsor delays in complete application submission
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 03-10-2022 03-10-2022 --- Yes
OCS Air Permit application submitted (Applicant Action) 06-10-2022 08-10-2022 --- Yes
OCS Air Permit application complete (Applicant Action) 09-09-2022 02-23-2023 --- No
Issuance of final decision/permit approval (Agency Action) 09-08-2023 01-22-2024 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 03-10-2022 03-10-2022 --- Yes
OCS Air Permit application submitted (Applicant Action) 06-10-2022 08-10-2022 --- Yes
OCS Air Permit application complete (Applicant Action) 09-09-2022 11-10-2022 --- No
Issuance of final decision/permit approval (Agency Action) 09-08-2023 01-22-2024 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 03-10-2022 03-10-2022 --- Yes
OCS Air Permit application submitted (Applicant Action) 08-10-2022 08-10-2022 --- No
OCS Air Permit application complete (Applicant Action) 11-10-2022 11-10-2022 --- No
Issuance of final decision/permit approval (Agency Action) 01-22-2024 01-22-2024 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) --- 03-10-2022 --- Yes
OCS Air Permit application submitted (Applicant Action) --- 06-10-2022 --- No
OCS Air Permit application complete (Applicant Action) --- 09-09-2022 --- No
Issuance of final decision/permit approval (Agency Action) --- 09-08-2023 --- No