Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 03-31-2022 08-12-2022 --- Yes
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 10-11-2022 04-10-2023 --- Yes
ESA Consultation Concludes (Agency Action) 03-10-2023 09-08-2023 --- Yes
In Progress
The second ESA milestone was met two days early.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 03-31-2022 08-12-2022 --- Yes
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 10-11-2022 04-10-2023 --- Yes
ESA Consultation Concludes (Agency Action) 03-10-2023 09-08-2023 --- No
Planned
On January 27, NOAA notified BOEM that the information necessary to initiate consultation was missing from the December 2022 BA.  NOAA requested that BOEM provide that information by February 27 so that it could be reviewed before the March 13 milestone date.  On February 8, BOEM informed NOAA that they would not be able to provide the information until after February 27 and requested that the milestone date be moved back by 30 days to April 12, 2023.  This also requires ESA milestone #3 to be delayed by 30 days in order to allow for the 150 days for NOAA to review and conclude consultation. As such, the ESA milestone #3 for "ESA Consultation Concludes" is being revised to September 8, 2023.    , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 03-31-2022 08-12-2022 --- Yes
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 10-11-2022 04-12-2023 --- No
ESA Consultation Concludes (Agency Action) 03-10-2023 09-08-2023 --- No
Planned
  On January 27 NMFS notified BOEM that information necessary to initiate consultation was missing from the December 2022 BA.  We requested that BOEM provide that information by February 27 so that it could be reviewed before the March 13 ESA initiation milestone date.  On February 8, BOEM informed us that they would not be able to provide the information until after February 27 and requested that the ESA initiation milestone date be moved back by 30 days to April 12, 2023.  This change in the ESA initiation milestone date also requires ESA milestone 3 (the final milestone) to be delayed by 30 days.     , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 03-31-2022 08-12-2022 --- Yes
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 10-11-2022 04-12-2023 --- No
ESA Consultation Concludes (Agency Action) 03-10-2023 08-10-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 03-31-2022 08-12-2022 --- Yes
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 10-11-2022 03-13-2023 --- No
ESA Consultation Concludes (Agency Action) 03-10-2023 08-10-2023 --- No
Planned
Original Target Date Data Entry Effort , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 03-31-2022 08-12-2022 --- No
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 10-11-2022 03-13-2023 --- No
ESA Consultation Concludes (Agency Action) 03-10-2023 08-10-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 08-12-2022 08-12-2022 --- No
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 03-13-2023 03-13-2023 --- No
ESA Consultation Concludes (Agency Action) 08-10-2023 08-10-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) --- 07-15-2022 --- No
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) --- 03-13-2023 --- No
ESA Consultation Concludes (Agency Action) --- 08-10-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) --- 04-29-2022 --- No
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) --- 11-14-2022 --- No
ESA Consultation Concludes (Agency Action) --- 04-13-2023 --- No