Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 10-15-2022 10-14-2022 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 11-14-2022 11-14-2022 --- Yes
Publication of Public Notice (Agency Action) 11-30-2022 05-05-2023 05-19-2023 Yes
Final Verification/Permit Decision Rendered (Agency Action) 12-22-2023 12-22-2023 12-16-2024 Yes
In Progress
The revised timeline shifts the 29 October 2024 final milestone to 16 December 2024 based on the USACE requirement for a 120-day review period to make a permit decision. The applicant was advised during meetings and in writing that the delayed submittal of required information would result in a day-for-day slip to the final milestone.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 10-15-2022 10-14-2022 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 11-14-2022 11-14-2022 --- Yes
Publication of Public Notice (Agency Action) 11-30-2022 05-05-2023 05-19-2023 Yes
Final Verification/Permit Decision Rendered (Agency Action) 12-22-2023 12-22-2023 12-16-2024 No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 10-15-2022 10-14-2022 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 11-14-2022 11-14-2022 --- Yes
Publication of Public Notice (Agency Action) 11-30-2022 05-05-2023 05-19-2023 Yes
Final Verification/Permit Decision Rendered (Agency Action) 12-22-2023 12-22-2023 10-29-2024 No
In Progress
Date needs to move 120-days after ROD (EIS milestone). The ROD date move is tied to the DEIS move date. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 10-15-2022 10-14-2022 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 11-14-2022 11-14-2022 --- Yes
Publication of Public Notice (Agency Action) 11-30-2022 05-05-2023 05-19-2023 Yes
Final Verification/Permit Decision Rendered (Agency Action) 12-22-2023 12-22-2023 07-23-2024 No
In Progress
Date needs to move 120-days after ROD (EIS milestone). The ROD date move is tied to the DEIS move date. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 10-15-2022 10-14-2022 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 11-14-2022 11-14-2022 --- Yes
Publication of Public Notice (Agency Action) 11-30-2022 05-05-2023 --- No
Final Verification/Permit Decision Rendered (Agency Action) 12-22-2023 12-22-2023 --- No
Planned
The application was submitted one day early. The Public Notice date was shifted to align with the BOEM NEPA process and will be issued at the same time as the Notice of Availability for the Draft Environmental Impact Statement.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 10-15-2022 10-14-2022 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 11-14-2022 11-14-2022 --- No
Publication of Public Notice (Agency Action) 11-30-2022 05-05-2023 --- No
Final Verification/Permit Decision Rendered (Agency Action) 12-22-2023 12-22-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 10-15-2022 10-15-2022 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 11-14-2022 11-14-2022 --- No
Publication of Public Notice (Agency Action) 11-30-2022 11-30-2022 --- No
Final Verification/Permit Decision Rendered (Agency Action) 12-22-2023 12-22-2023 --- No