USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 03-25-2021 03-25-2021 --- Yes
Application deemed complete (Agency Action) 06-29-2021 06-29-2021 --- Yes
Final decision/agency action (Agency Action) 12-22-2023 09-30-2024 --- Yes
In Progress
Project sponsor delays in providing the required Coastal Zone Management Act (CZMA)-related application to the state of New Jersey is causing a delay in completion of the Federal consistency review and decision, which is needed prior to BOEM issuing a construction and operations plan (COP) decision. Generally, BOEM requires the consistency determination be complete 90-days prior to the Record of Decision (ROD).
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 03-25-2021 03-25-2021 --- Yes
Application deemed complete (Agency Action) 06-29-2021 06-29-2021 --- Yes
Final decision/agency action (Agency Action) 12-22-2023 09-30-2024 --- No
In Progress
The Delay to the DEIS due to the sponsor not providing sufficient documents , and revisions to the project design envelope as late as 3/13/2023 that requires the COP end date to move as the ROD (Under the EIS milestone) must be issued before the COP agency decision can be made.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 03-25-2021 03-25-2021 --- Yes
Application deemed complete (Agency Action) 06-29-2021 06-29-2021 --- Yes
Final decision/agency action (Agency Action) 12-22-2023 06-24-2024 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 03-25-2021 03-25-2021 --- Yes
Application deemed complete (Agency Action) 06-29-2021 06-29-2021 --- Yes
Final decision/agency action (Agency Action) 12-22-2023 12-22-2023 --- No