Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 03-25-2021 03-25-2021 --- Yes
Application deemed complete (Agency Action) 06-29-2021 06-29-2021 --- Yes
Final decision/agency action (Agency Action) 12-22-2023 09-30-2024 --- Yes
In Progress
Project sponsor delays in providing the required Coastal Zone Management Act (CZMA)-related application to the state of New Jersey is causing a delay in completion of the Federal consistency review and decision, which is needed prior to BOEM issuing a construction and operations plan (COP) decision. Generally, BOEM requires the consistency determination be complete 90-days prior to the Record of Decision (ROD). , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 03-25-2021 03-25-2021 --- Yes
Application deemed complete (Agency Action) 06-29-2021 06-29-2021 --- Yes
Final decision/agency action (Agency Action) 12-22-2023 09-30-2024 --- No
In Progress
The Delay to the DEIS due to the sponsor not providing sufficient documents , and revisions to the project design envelope as late as 3/13/2023 that requires the COP end date to move as the ROD (Under the EIS milestone) must be issued before the COP agency decision can be made. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 03-25-2021 03-25-2021 --- Yes
Application deemed complete (Agency Action) 06-29-2021 06-29-2021 --- Yes
Final decision/agency action (Agency Action) 12-22-2023 06-24-2024 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 03-25-2021 03-25-2021 --- Yes
Application deemed complete (Agency Action) 06-29-2021 06-29-2021 --- Yes
Final decision/agency action (Agency Action) 12-22-2023 12-22-2023 --- No