USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

Complete
EPA completed the final milestone for this action on April 15, 2024 which was in advance of the previously posted target date of May 1, 2024.  
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 08-13-2020 01-28-2022 --- Yes
OCS Air Permit application submitted (Applicant Action) 11-15-2022 10-07-2022 --- Yes
OCS Air Permit application complete (Applicant Action) 04-22-2023 02-13-2023 --- Yes
Issuance of final decision/permit approval (Agency Action) 10-01-2023 04-15-2024 --- Yes
In Progress
The EPA requires 30 days after BOEM’s issuance of the ROD in order to conduct a review of the ROD prior to issuing their air permitting decision. With the shift in the ROD date to April 1, an extension of the milestone date for the issuance of final decision for permit/approval of the OCS Air Permit action to May 1, 2024, is requested.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 08-13-2020 01-28-2022 --- Yes
OCS Air Permit application submitted (Applicant Action) 11-15-2022 10-07-2022 --- Yes
OCS Air Permit application complete (Applicant Action) 04-22-2023 02-13-2023 --- Yes
Issuance of final decision/permit approval (Agency Action) 10-01-2023 05-01-2024 --- No
In Progress
BOEM requests an extension of the final completion date for the OCS air permit based on a one-year statutory deadline provided by  the Clean Air Act for EPA to reach an OCS air permitting decision, following their determination that a project sponsor has submitted a complete application. Here, EPA deemed the Project Sponsor’s OCS air permit application complete on February 13, 2023, after spending about four months engaging with the Project Sponsor on deficiencies EPA found in the Project Sponsor’s initial application submission. Accordingly, the requested final completion date for the OCS air permit action is February 13, 2024.  
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 08-13-2020 01-28-2022 --- Yes
OCS Air Permit application submitted (Applicant Action) 11-15-2022 10-07-2022 --- Yes
OCS Air Permit application complete (Applicant Action) 04-22-2023 02-13-2023 --- Yes
Issuance of final decision/permit approval (Agency Action) 10-01-2023 02-13-2024 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 08-13-2020 01-28-2022 --- Yes
OCS Air Permit application submitted (Applicant Action) 11-15-2022 10-07-2022 --- Yes
OCS Air Permit application complete (Applicant Action) 04-22-2023 02-13-2023 --- Yes
Issuance of final decision/permit approval (Agency Action) 10-01-2023 10-01-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 08-13-2020 01-28-2022 --- Yes
OCS Air Permit application submitted (Applicant Action) 11-15-2022 10-07-2022 --- Yes
OCS Air Permit application complete (Applicant Action) 04-22-2023 02-13-2023 --- No
Issuance of final decision/permit approval (Agency Action) 10-01-2023 10-01-2023 --- No
Planned
Project schedule delays resulted in changes to the EIS and ROD dates. 
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 08-13-2020 01-28-2022 --- Yes
OCS Air Permit application submitted (Applicant Action) 11-15-2022 10-07-2022 --- Yes
OCS Air Permit application complete (Applicant Action) 04-22-2023 01-18-2023 --- No
Issuance of final decision/permit approval (Agency Action) 10-01-2023 10-01-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 08-13-2020 01-28-2022 --- Yes
OCS Air Permit application submitted (Applicant Action) 11-15-2022 10-20-2022 --- No
OCS Air Permit application complete (Applicant Action) 04-22-2023 01-18-2023 --- No
Issuance of final decision/permit approval (Agency Action) 10-01-2023 10-01-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 01-28-2022 01-28-2022 --- Yes
OCS Air Permit application submitted (Applicant Action) 09-29-2022 09-29-2022 --- No
OCS Air Permit application complete (Applicant Action) 04-22-2023 04-22-2023 --- No
Issuance of final decision/permit approval (Agency Action) 10-01-2023 10-01-2023 --- No