Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 09-01-2021 12-23-2022 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 11-15-2022 04-06-2023 --- Yes
ESA Consultation Concludes (Agency Action) 04-23-2023 04-23-2023 09-28-2023 Yes
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 09-01-2021 12-23-2022 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 11-15-2022 04-06-2023 --- Yes
ESA Consultation Concludes (Agency Action) 04-23-2023 04-23-2023 09-29-2023 No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 09-01-2021 12-23-2022 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 11-15-2022 04-06-2023 --- Yes
ESA Consultation Concludes (Agency Action) 04-23-2023 04-23-2023 08-21-2023 No
In Progress
Milestone completed 04/06, 1-day earlier than previous target date of 04/07. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 09-01-2021 12-23-2022 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 11-15-2022 04-06-2023 --- Yes
ESA Consultation Concludes (Agency Action) 04-23-2023 04-23-2023 --- No
Planned
Due to staffing uncertainty and competing workload demand on other very high priority projects, FWS and BOEM have agreed to extend this milestone by 30 days. Provided the consultation package is complete at that time, BOEM and FWS anticipate moving the completion date of the consultation to August 2023 to allow time for formal consultation per ESA regulations. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 09-01-2021 12-23-2022 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 11-15-2022 04-07-2023 --- No
ESA Consultation Concludes (Agency Action) 04-23-2023 04-23-2023 --- No
Planned
This Milestone revision is based on project schedule changes resulted in revisions to the EIS and ROD dates. This date will allow adequate time for coordination between BOEM and FWS, and to complete formal consultation, if needed. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 09-01-2021 12-23-2022 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 11-15-2022 03-08-2023 --- No
ESA Consultation Concludes (Agency Action) 04-23-2023 04-23-2023 --- No
Planned
Overall project schedule changes necessitates a change in the consultation schedule to better align the two and reflect when the lead agency anticipates submitting a complete consultation package. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 09-01-2021 12-23-2022 --- No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 11-15-2022 03-08-2023 --- No
ESA Consultation Concludes (Agency Action) 04-23-2023 04-23-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 09-01-2021 11-10-2022 --- No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 11-15-2022 01-27-2023 --- No
ESA Consultation Concludes (Agency Action) 04-23-2023 04-23-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 11-10-2022 11-10-2022 --- No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 01-27-2023 01-27-2023 --- No
ESA Consultation Concludes (Agency Action) 04-23-2023 04-23-2023 --- No