Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 08-01-2022 08-01-2022 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 08-15-2022 12-08-2022 --- Yes
Publication of Public Notice (Agency Action) 08-30-2022 12-23-2022 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 10-01-2023 07-01-2024 --- Yes
In Progress
The Section 10 Rivers and Harbors Act of 1899 and Section 404 Clean Water Act final verification/permit decision rendered milestone date is dependent upon BOEM’s EIS action ROD issuance date. USACE requires 90-days between issuance of the ROD and issuance of USACE’s Section 10/404 decision. Therefore, an extension of the Section 10/404 final completion date is requested based upon the extension of the ROD issuance date.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 08-01-2022 08-01-2022 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 08-15-2022 12-08-2022 --- Yes
Publication of Public Notice (Agency Action) 08-30-2022 12-23-2022 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 10-01-2023 07-01-2024 --- No
In Progress
Update: the milestone has been adjusted in accordance with BOEM's revised schedule.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 08-01-2022 08-01-2022 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 08-15-2022 12-08-2022 --- Yes
Publication of Public Notice (Agency Action) 08-30-2022 12-23-2022 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 10-01-2023 03-25-2024 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 08-01-2022 08-01-2022 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 08-15-2022 12-08-2022 --- Yes
Publication of Public Notice (Agency Action) 08-30-2022 12-23-2022 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 10-01-2023 10-01-2023 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 08-01-2022 08-01-2022 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 08-15-2022 12-08-2022 --- Yes
Publication of Public Notice (Agency Action) 08-30-2022 12-23-2022 --- No
Final Verification/Permit Decision Rendered (Agency Action) 10-01-2023 10-01-2023 --- No
Planned
Project schedule delays resulted in changes to EIS dates. 
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 08-01-2022 08-01-2022 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 08-15-2022 12-08-2022 --- No
Publication of Public Notice (Agency Action) 08-30-2022 12-23-2022 --- No
Final Verification/Permit Decision Rendered (Agency Action) 10-01-2023 10-01-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 08-01-2022 08-01-2022 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 08-15-2022 10-10-2022 --- No
Publication of Public Notice (Agency Action) 08-30-2022 10-25-2022 --- No
Final Verification/Permit Decision Rendered (Agency Action) 10-01-2023 10-01-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 08-01-2022 08-01-2022 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 10-10-2022 10-10-2022 --- No
Publication of Public Notice (Agency Action) 10-25-2022 10-25-2022 --- No
Final Verification/Permit Decision Rendered (Agency Action) 10-01-2023 10-01-2023 --- No