Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ITA Application Submitted (Applicant Action) 12-01-2021 12-01-2021 --- Yes
NOAA Determines ITA Application is Complete (Applicant Action) 04-01-2022 07-20-2022 --- Yes
Publish Notice of Receipt in Federal Register (LOA Only) (Agency Action) 05-02-2022 08-22-2022 --- Yes
Publish Proposed ITA in Federal Register (Agency Action) 11-22-2022 05-22-2023 06-06-2023 Yes
Publish Final ITA Regulations in Federal Register (LOA Only) (Agency Action) 08-23-2023 01-22-2024 06-21-2024 Yes
ITA decision rendered (Agency Action) 09-23-2023 12-28-2023 07-22-2024 Yes
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ITA Application Submitted (Applicant Action) 12-01-2021 12-01-2021 --- Yes
NOAA Determines ITA Application is Complete (Applicant Action) 04-01-2022 07-20-2022 --- Yes
Publish Notice of Receipt in Federal Register (LOA Only) (Agency Action) 05-02-2022 08-22-2022 --- Yes
Publish Proposed ITA in Federal Register (Agency Action) 11-22-2022 05-22-2023 06-06-2023 Yes
Publish Final ITA Regulations in Federal Register (LOA Only) (Agency Action) 08-23-2023 01-22-2024 06-21-2024 Yes
ITA decision rendered (Agency Action) 09-23-2023 12-28-2023 07-22-2024 No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ITA Application Submitted (Applicant Action) 12-01-2021 12-01-2021 --- Yes
NOAA Determines ITA Application is Complete (Applicant Action) 04-01-2022 07-20-2022 --- Yes
Publish Notice of Receipt in Federal Register (LOA Only) (Agency Action) 05-02-2022 08-22-2022 --- Yes
Publish Proposed ITA in Federal Register (Agency Action) 11-22-2022 05-22-2023 06-06-2023 Yes
Publish Final ITA Regulations in Federal Register (LOA Only) (Agency Action) 08-23-2023 01-22-2024 06-21-2024 No
ITA decision rendered (Agency Action) 09-23-2023 12-28-2023 07-22-2024 No
In Progress
BOEM revised the ROD date to be 4/1/24.  The final two MMPA milestones were updated according to the nominal timeline, which places the final ITA regulation publication in the Federal Register 60 days after the ROD and the ITA decision rendered 30 days after publishing the final ITA regulations.   , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ITA Application Submitted (Applicant Action) 12-01-2021 12-01-2021 --- Yes
NOAA Determines ITA Application is Complete (Applicant Action) 04-01-2022 07-20-2022 --- Yes
Publish Notice of Receipt in Federal Register (LOA Only) (Agency Action) 05-02-2022 08-22-2022 --- Yes
Publish Proposed ITA in Federal Register (Agency Action) 11-22-2022 05-22-2023 06-06-2023 Yes
Publish Final ITA Regulations in Federal Register (LOA Only) (Agency Action) 08-23-2023 01-22-2024 05-31-2024 No
ITA decision rendered (Agency Action) 09-23-2023 12-28-2023 07-01-2024 No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ITA Application Submitted (Applicant Action) 12-01-2021 12-01-2021 --- Yes
NOAA Determines ITA Application is Complete (Applicant Action) 04-01-2022 07-20-2022 --- Yes
Publish Notice of Receipt in Federal Register (LOA Only) (Agency Action) 05-02-2022 08-22-2022 --- Yes
Publish Proposed ITA in Federal Register (Agency Action) 11-22-2022 05-22-2023 06-06-2023 Yes
Publish Final ITA Regulations in Federal Register (LOA Only) (Agency Action) 08-23-2023 01-22-2024 02-26-2024 No
ITA decision rendered (Agency Action) 09-23-2023 12-28-2023 03-27-2024 No
In Progress
MMPA proposed rule, final rule, and ITA decision rendered milestones are shifted by 60 days because Park City Wind submitted new density, take, and project description information necessary to inform the proposed rule on January 13, 2023. The 60-day push allowed time for review of that information and incorporation into the draft proposed rule. The final two MMPA milestones are also shifted 60 days to allow for a minimum of eight months between the proposed and final rule. At that time, NMFS noted the final rule and LOA may change again if BOEM changes the FEIS/ROD schedule. BOEM did shift the EIS schedule due to the project sponsor delay, so NMFS has revised dates accordingly. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ITA Application Submitted (Applicant Action) 12-01-2021 12-01-2021 --- Yes
NOAA Determines ITA Application is Complete (Applicant Action) 04-01-2022 07-20-2022 --- Yes
Publish Notice of Receipt in Federal Register (LOA Only) (Agency Action) 05-02-2022 08-22-2022 --- Yes
Publish Proposed ITA in Federal Register (Agency Action) 11-22-2022 06-05-2023 06-06-2023 No
Publish Final ITA Regulations in Federal Register (LOA Only) (Agency Action) 08-23-2023 02-26-2024 02-26-2024 No
ITA decision rendered (Agency Action) 09-23-2023 03-27-2024 03-27-2024 No
In Progress
The MMPA proposed rule, final rule, and ITA decision rendered milestones are shifted by 60 days because Park City Wind submitted new density, take, and project description information necessary to inform the proposed rule on January 13, 2023. The 60-day push allowed time for review of that information and incorporation into the draft proposed rule. The final two MMPA milestones are also shifted 60 days to allow for a minimum of eight months between the proposed and final rule. At that time, NMFS noted the final rule and LOA may change again if BOEM changes the FEIS/ROD schedule.  BOEM did shift the EIS schedule due to the project sponsor delay, so NMFS has revised dates accordingly.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ITA Application Submitted (Applicant Action) 12-01-2021 12-01-2021 --- Yes
NOAA Determines ITA Application is Complete (Applicant Action) 04-01-2022 07-20-2022 --- Yes
Publish Notice of Receipt in Federal Register (LOA Only) (Agency Action) 05-02-2022 08-22-2022 --- Yes
Publish Proposed ITA in Federal Register (Agency Action) 11-22-2022 06-05-2023 --- No
Publish Final ITA Regulations in Federal Register (LOA Only) (Agency Action) 08-23-2023 02-26-2024 --- No
ITA decision rendered (Agency Action) 09-23-2023 03-27-2024 --- No
In Progress
The MMPA proposed rule, final rule, and ITA decision rendered milestones are shifting by 60 days. Park City Wind submitted new density, take, and project description information necessary to inform the proposed rule on January 13, 2023. The 60-day push allows for review of that information and incorporation into the draft proposed rule. The final two MMPA milestones are also shifting 60 days to allow for a minimum of eight months between the proposed and final rule. NMFS notes the final rule and LOA may change again if BOEM changes the FEIS/ROD schedule. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ITA Application Submitted (Applicant Action) 12-01-2021 12-01-2021 --- Yes
NOAA Determines ITA Application is Complete (Applicant Action) 04-01-2022 07-20-2022 --- Yes
Publish Notice of Receipt in Federal Register (LOA Only) (Agency Action) 05-02-2022 08-22-2022 --- Yes
Publish Proposed ITA in Federal Register (Agency Action) 11-22-2022 05-22-2023 --- No
Publish Final ITA Regulations in Federal Register (LOA Only) (Agency Action) 08-23-2023 01-22-2024 --- No
ITA decision rendered (Agency Action) 09-23-2023 12-28-2023 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ITA Application Submitted (Applicant Action) 12-01-2021 12-01-2021 --- Yes
NOAA Determines ITA Application is Complete (Applicant Action) 04-01-2022 07-20-2022 --- Yes
Publish Notice of Receipt in Federal Register (LOA Only) (Agency Action) 05-02-2022 08-22-2022 --- Yes
Publish Proposed ITA in Federal Register (Agency Action) 11-22-2022 03-21-2023 --- No
Publish Final ITA Regulations in Federal Register (LOA Only) (Agency Action) 08-23-2023 11-28-2023 --- No
ITA decision rendered (Agency Action) 09-23-2023 12-28-2023 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ITA Application Submitted (Applicant Action) --- --- --- No
NOAA Determines ITA Application is Complete (Applicant Action) 07-21-2022 07-20-2022 --- Yes
Publish Notice of Receipt in Federal Register (LOA Only) (Agency Action) 08-22-2022 08-22-2022 --- No
Publish Proposed ITA in Federal Register (Agency Action) 03-21-2023 03-21-2023 --- No
Publish Final ITA Regulations in Federal Register (LOA Only) (Agency Action) 11-28-2023 11-28-2023 --- No
ITA decision rendered (Agency Action) 12-28-2023 12-28-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ITA Application Submitted (Applicant Action) --- --- --- No
NOAA Determines ITA Application is Complete (Applicant Action) 07-21-2022 07-21-2022 --- No
Publish Notice of Receipt in Federal Register (LOA Only) (Agency Action) 08-22-2022 08-22-2022 --- No
Publish Proposed ITA in Federal Register (Agency Action) 03-21-2023 03-21-2023 --- No
Publish Final ITA Regulations in Federal Register (LOA Only) (Agency Action) 11-28-2023 11-28-2023 --- No
ITA decision rendered (Agency Action) 12-28-2023 12-28-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOAA Determines ITA Application is Complete (Applicant Action) --- 07-05-2022 --- No
Publish Notice of Receipt in Federal Register (LOA Only) (Agency Action) --- 08-05-2022 --- No
Publish Proposed ITA in Federal Register (Agency Action) --- 03-06-2023 --- No
Publish Final ITA Regulations in Federal Register (LOA Only) (Agency Action) --- 11-28-2023 --- No
ITA decision rendered (Agency Action) --- 12-28-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOAA Determines ITA Application is Complete (Applicant Action) --- 06-02-2022 --- No
Publish Notice of Receipt in Federal Register (LOA Only) (Agency Action) --- 07-05-2022 --- No
Publish Proposed ITA in Federal Register (Agency Action) --- 02-02-2023 --- No
Publish Final ITA Regulations in Federal Register (LOA Only) (Agency Action) --- 11-21-2023 --- No
ITA decision rendered (Agency Action) --- 12-21-2023 --- No