Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 06-30-2021 06-30-2021 --- Yes
Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action) 06-16-2021 06-16-2021 --- Yes
Section 106 consultation concluded (Agency Action) 06-23-2023 03-01-2024 --- Yes
In Progress
 Two Tribes have requested additional consultation to incorporate their feedback and comments prior to finalizing the Section 106 Memorandum of Agreement (MOA) for signature by consulting parties. The requested date affords time to hold the requested government-to-government consultations for the two Tribes and, thereafter, to hold a fifth consulting party meeting in early January 2024 on the final Section 106 MOA. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 06-30-2021 06-30-2021 --- Yes
Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action) 06-16-2021 06-16-2021 --- Yes
Section 106 consultation concluded (Agency Action) 06-23-2023 03-01-2024 --- No
In Progress
  BOEM is meeting its Section 106 consultation obligations through the Section 106 NEPA substitution process, the Section 106 consultation will conclude simultaneously with issuance of the ROD for NEPA.   , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 06-30-2021 06-30-2021 --- Yes
Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action) 06-16-2021 06-16-2021 --- Yes
Section 106 consultation concluded (Agency Action) 06-23-2023 12-26-2023 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 06-30-2021 06-30-2021 --- Yes
Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action) 06-16-2021 06-16-2021 --- Yes
Section 106 consultation concluded (Agency Action) 06-23-2023 06-23-2023 --- No