USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

Complete
Final milestone, issuance of decision, was ahead of the March 20 scheduled date. The milestone was completed on March 11.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 01-16-2023 01-13-2023 --- Yes
Completeness Determination (Agency Action) 02-15-2023 02-13-2023 --- Yes
Complete application submitted (Applicant Action) 04-17-2023 08-21-2023 --- Yes
Issuance of Decision (Agency Action) 02-20-2024 03-11-2024 --- Yes
In Progress
Milestone updated as per BOEM's revised ROD date. BOEM ROD date shifted from October 23 2023 to November 21 2023 and the USACE final milestone has been adjusted accordingly. 
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 01-16-2023 01-13-2023 --- Yes
Completeness Determination (Agency Action) 02-15-2023 02-13-2023 --- Yes
Complete application submitted (Applicant Action) 04-17-2023 08-21-2023 --- Yes
Issuance of Decision (Agency Action) 02-20-2024 03-20-2024 --- No
In Progress
With the latest documentation provided by the applicant, the USACE has determined that the Section 408 application is now complete; the applicant was sent written notification on Aug 21, 2023. The USACE was able to determine that the application was complete prior to the Sept 5, 2023 milestone date. 
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 01-16-2023 01-13-2023 --- Yes
Completeness Determination (Agency Action) 02-15-2023 02-13-2023 --- Yes
Complete application submitted (Applicant Action) 04-17-2023 08-21-2023 --- Yes
Issuance of Decision (Agency Action) 02-20-2024 02-20-2024 --- No
In Progress
The applicant has not provided all technical documentation for a complete application. The USACE has notified the applicant of what materials are required to complete the application.    8-9-23 -- Ann D. was able to get confirmation yesterday from the District that they did receive additional documentation. USACE has 30 days from 8/4 to review, so please change the date to 9/5/23.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 01-16-2023 01-13-2023 --- Yes
Completeness Determination (Agency Action) 02-15-2023 02-13-2023 --- Yes
Complete application submitted (Applicant Action) 04-17-2023 09-05-2023 --- No
Issuance of Decision (Agency Action) 02-20-2024 02-20-2024 --- No
In Progress
The applicant has not provided adequate information for a complete application. The applicant was notified of the remaining required documentation. 
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 01-16-2023 01-13-2023 --- Yes
Completeness Determination (Agency Action) 02-15-2023 02-13-2023 --- Yes
Complete application submitted (Applicant Action) 04-17-2023 08-15-2023 --- No
Issuance of Decision (Agency Action) 02-20-2024 02-20-2024 --- No
In Progress
The applicant was informed in writing of missing application materials upon issuance of the completeness determination. The applicant is working on compiling the remaining materials. All materials will not be ready by 17 April 2023, so the date has been moved 60 days. 
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 01-16-2023 01-13-2023 --- Yes
Completeness Determination (Agency Action) 02-15-2023 02-13-2023 --- Yes
Complete application submitted (Applicant Action) 04-17-2023 06-16-2023 --- No
Issuance of Decision (Agency Action) 02-20-2024 02-20-2024 --- No
In Progress
The New York District was able to complete the application review for a completeness determination a couple of days early. 
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 01-16-2023 01-13-2023 --- Yes
Completeness Determination (Agency Action) 02-15-2023 02-13-2023 --- Yes
Complete application submitted (Applicant Action) 04-17-2023 04-17-2023 --- No
Issuance of Decision (Agency Action) 02-20-2024 02-20-2024 --- No
Planned
Applicant submitted application ahead of schedule. 
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 01-16-2023 01-13-2023 --- Yes
Completeness Determination (Agency Action) 02-15-2023 02-15-2023 --- No
Complete application submitted (Applicant Action) 04-17-2023 04-17-2023 --- No
Issuance of Decision (Agency Action) 02-20-2024 02-20-2024 --- No
Planned
It was determined that a 408 permission is required for the Empire Wind proposal due to an overlap with a USACE Civil Works constructed project. The 408 milestones should now be displayed on the dashboard. 
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 01-16-2023 01-16-2023 --- No
Completeness Determination (Agency Action) 02-15-2023 02-15-2023 --- No
Complete application submitted (Applicant Action) 04-17-2023 04-17-2023 --- No
Issuance of Decision (Agency Action) 02-20-2024 02-20-2024 --- No