USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

Complete
EPA signed the permit ahead of schedule.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 05-05-2020 05-05-2020 --- Yes
OCS Air Permit application submitted (Applicant Action) 05-01-2022 05-01-2022 --- Yes
OCS Air Permit application complete (Applicant Action) 08-01-2022 10-07-2022 --- Yes
Issuance of final decision/permit approval (Agency Action) 07-31-2023 09-28-2023 --- Yes
In Progress
Applicant delays caused delay in EPA’s application completeness determination, which shifted final decision milestone date forward according to the one-year statutory deadline under CAA § 165.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 05-05-2020 05-05-2020 --- Yes
OCS Air Permit application submitted (Applicant Action) 05-01-2022 05-01-2022 --- Yes
OCS Air Permit application complete (Applicant Action) 08-01-2022 10-07-2022 --- Yes
Issuance of final decision/permit approval (Agency Action) 07-31-2023 10-06-2023 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 05-05-2020 05-05-2020 --- Yes
OCS Air Permit application submitted (Applicant Action) 05-01-2022 05-01-2022 --- Yes
OCS Air Permit application complete (Applicant Action) 08-01-2022 10-07-2022 --- Yes
Issuance of final decision/permit approval (Agency Action) 07-31-2023 07-31-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 05-05-2020 05-05-2020 --- Yes
OCS Air Permit application submitted (Applicant Action) 05-01-2022 05-01-2022 --- Yes
OCS Air Permit application complete (Applicant Action) 08-01-2022 10-07-2022 --- No
Issuance of final decision/permit approval (Agency Action) 07-31-2023 07-31-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 05-05-2020 05-05-2020 --- Yes
OCS Air Permit application submitted (Applicant Action) 05-01-2022 05-01-2022 --- Yes
OCS Air Permit application complete (Applicant Action) 10-05-2022 10-05-2022 --- No
Issuance of final decision/permit approval (Agency Action) 07-31-2023 07-31-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) --- 05-05-2020 --- Yes
OCS Air Permit application submitted (Applicant Action) --- 05-01-2022 --- Yes
OCS Air Permit application complete (Applicant Action) --- 08-01-2022 --- No
Issuance of final decision/permit approval (Agency Action) --- 07-31-2023 --- No