Permitting Action Modification History

Complete
EPA signed the permit ahead of schedule. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 05-05-2020 05-05-2020 --- Yes
OCS Air Permit application submitted (Applicant Action) 05-01-2022 05-01-2022 --- Yes
OCS Air Permit application complete (Applicant Action) 08-01-2022 10-07-2022 --- Yes
Issuance of final decision/permit approval (Agency Action) 07-31-2023 09-28-2023 --- Yes
In Progress
Applicant delays caused delay in EPA’s application completeness determination, which shifted final decision milestone date forward according to the one-year statutory deadline under CAA § 165. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 05-05-2020 05-05-2020 --- Yes
OCS Air Permit application submitted (Applicant Action) 05-01-2022 05-01-2022 --- Yes
OCS Air Permit application complete (Applicant Action) 08-01-2022 10-07-2022 --- Yes
Issuance of final decision/permit approval (Agency Action) 07-31-2023 10-06-2023 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 05-05-2020 05-05-2020 --- Yes
OCS Air Permit application submitted (Applicant Action) 05-01-2022 05-01-2022 --- Yes
OCS Air Permit application complete (Applicant Action) 08-01-2022 10-07-2022 --- Yes
Issuance of final decision/permit approval (Agency Action) 07-31-2023 07-31-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 05-05-2020 05-05-2020 --- Yes
OCS Air Permit application submitted (Applicant Action) 05-01-2022 05-01-2022 --- Yes
OCS Air Permit application complete (Applicant Action) 08-01-2022 10-07-2022 --- No
Issuance of final decision/permit approval (Agency Action) 07-31-2023 07-31-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 05-05-2020 05-05-2020 --- Yes
OCS Air Permit application submitted (Applicant Action) 05-01-2022 05-01-2022 --- Yes
OCS Air Permit application complete (Applicant Action) 10-05-2022 10-05-2022 --- No
Issuance of final decision/permit approval (Agency Action) 07-31-2023 07-31-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) --- 05-05-2020 --- Yes
OCS Air Permit application submitted (Applicant Action) --- 05-01-2022 --- Yes
OCS Air Permit application complete (Applicant Action) --- 08-01-2022 --- No
Issuance of final decision/permit approval (Agency Action) --- 07-31-2023 --- No