Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 02-15-2022 04-25-2022 --- Yes
NOAA determines EFH Assessment is Complete (Agency Action) 08-01-2022 12-01-2022 03-23-2023 Yes
NOAA Issues any EFH Conservation Recommendations (Agency Action) 09-30-2022 03-01-2023 06-16-2023 Yes
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 02-15-2022 04-25-2022 --- Yes
NOAA determines EFH Assessment is Complete (Agency Action) 08-01-2022 12-01-2022 03-23-2023 Yes
NOAA Issues any EFH Conservation Recommendations (Agency Action) 09-30-2022 03-01-2023 06-21-2023 No
In Progress
Email received stating NMFS initiated EFH consultation effective March 23, 2023. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 02-15-2022 04-25-2022 --- Yes
NOAA determines EFH Assessment is Complete (Agency Action) 08-01-2022 12-01-2022 03-23-2023 Yes
NOAA Issues any EFH Conservation Recommendations (Agency Action) 09-30-2022 03-01-2023 07-07-2023 No
Planned
While BOEM provided a revised EFH Assessment on August 29,2022, it did not address critical information needs in NMFS' June, 24, 2022 request for additional information.  The 30-day extension of the remaining EFH milestones will allow BOEM time to revise its EFH Assessment to address concerns these concerns.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 02-15-2022 04-25-2022 --- Yes
NOAA determines EFH Assessment is Complete (Agency Action) 08-01-2022 12-01-2022 --- No
NOAA Issues any EFH Conservation Recommendations (Agency Action) 09-30-2022 03-01-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) --- 04-25-2022 --- Yes
NOAA determines EFH Assessment is Complete (Agency Action) --- 11-01-2022 --- No
NOAA Issues any EFH Conservation Recommendations (Agency Action) --- 01-30-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) --- 04-25-2022 --- No
NOAA determines EFH Assessment is Complete (Agency Action) --- 11-01-2022 --- No
NOAA Issues any EFH Conservation Recommendations (Agency Action) --- 01-30-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) --- 04-14-2022 --- No
NOAA determines EFH Assessment is Complete (Agency Action) --- 10-28-2022 --- No
NOAA Issues any EFH Conservation Recommendations (Agency Action) --- 01-26-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) --- 03-15-2022 --- No
NOAA determines EFH Assessment is Complete (Agency Action) --- 09-27-2022 --- No
NOAA Issues any EFH Conservation Recommendations (Agency Action) --- 12-06-2022 --- No