Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 03-30-2021 03-30-2021 --- Yes
Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action) 03-30-2021 03-30-2021 --- Yes
Section 106 consultation concluded (Agency Action) 03-31-2023 05-26-2023 06-30-2023 Yes
In Progress
Additional time was needed for consulting party review of the revised Section 106 MOA and supplemental technical memorandums to the Historic Resources Visual Effects Assessment (HRVEA) and Terrestrial Archaeological Resources Assessment (TARA) reports, prepared by Ocean Wind LLC. BOEM has distributed the Section 106 MOA and signatures are anticipated within 30 calendar days, by June 30, 2023.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 03-30-2021 03-30-2021 --- Yes
Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action) 03-30-2021 03-30-2021 --- Yes
Section 106 consultation concluded (Agency Action) 03-31-2023 05-26-2023 06-30-2023 No
In Progress
The revised Section 106 technical reports, revised Finding of Effect, and revised draft Memorandum of Agreement (MOA) were distributed to consulting parties on November 11, 2022 for a 30-day review. On December 12, 2022, BOEM received comments that will require additional revisions to the Finding of Effect and MOA and subsequent consulting party review of those documents. Realignment of the final Section 106 Review milestone from April 14, 2023 to May 26, 2023 is needed to accommodate the additional review period for the revised Finding of Effect and revised MOA. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 03-30-2021 03-30-2021 --- Yes
Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action) 03-30-2021 03-30-2021 --- Yes
Section 106 consultation concluded (Agency Action) 03-31-2023 05-26-2023 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 03-30-2021 03-30-2021 --- Yes
Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action) 03-30-2021 03-30-2021 --- Yes
Section 106 consultation concluded (Agency Action) 03-31-2023 04-14-2023 --- No