USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Portions of this site may be affected due to a lapse in appropriations and associated shutdown/furloughs. Please monitor this page for updates on site availability and operating status.

Permitting Action Modification History

Paused
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 12-29-2021 09-14-2021 --- Yes
OCS Air Permit application submitted (Applicant Action) 03-29-2022 03-29-2022 --- Yes
OCS Air Permit application complete (Applicant Action) 06-29-2022 07-18-2022 --- Yes
Issuance of final decision/permit approval (Agency Action) 06-29-2023 12-13-2024 --- No
In Progress
Though EPA deemed the Project Sponsor’s OCS air permit application complete on January 4, 2023, further technical review of the modeling analyses showed that the magnitude of the air quality impacts was in violation Air Quality Standards, which rendered the application as submitted unapprovable. The application review was paused, and EPA requested that the application and/or modeling analyses be revised to correct any air quality violations. The Project Sponsor submitted a revised application with new information in August 2023, which superseded the original application and was incomplete. The Project Sponsor provided supplemental submittals in October 2023 and additional revised modeling on November 13, 2023. On October 31, 2023, the Project Sponsor announced that they would cease development of the Ocean Wind 1 Project, but later informed EPA that they intend to retain the lease and assets (permit actions) and continue to pursue an OCS air permit.  The November 13, 2023, submittal is undergoing review for completeness. If EPA determines on December 13, 2023, that the August 2023 permit application is complete, the Clean Air Act gives EPA one year from the completeness determination to issue a final permit decision.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 12-29-2021 09-14-2021 --- Yes
OCS Air Permit application submitted (Applicant Action) 03-29-2022 03-29-2022 --- Yes
OCS Air Permit application complete (Applicant Action) 06-29-2022 07-18-2022 --- Yes
Issuance of final decision/permit approval (Agency Action) 06-29-2023 12-13-2024 --- No
In Progress
Applicant delays caused delay in EPA’s application completeness determination, which shifted final decision milestone date forward according to the one-year statutory deadline under CAA § 165.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 12-29-2021 09-14-2021 --- Yes
OCS Air Permit application submitted (Applicant Action) 03-29-2022 03-29-2022 --- Yes
OCS Air Permit application complete (Applicant Action) 06-29-2022 07-18-2022 --- Yes
Issuance of final decision/permit approval (Agency Action) 06-29-2023 01-04-2024 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 09-14-2021 09-14-2021 --- Yes
OCS Air Permit application submitted (Applicant Action) 03-29-2022 03-29-2022 --- Yes
OCS Air Permit application complete (Applicant Action) 07-15-2022 07-18-2022 --- Yes
Issuance of final decision/permit approval (Agency Action) 06-29-2023 06-29-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 09-14-2021 09-14-2021 --- Yes
OCS Air Permit application submitted (Applicant Action) 03-29-2022 03-29-2022 --- Yes
OCS Air Permit application complete (Applicant Action) 07-15-2022 07-15-2022 --- No
Issuance of final decision/permit approval (Agency Action) 06-29-2023 06-29-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) --- 09-14-2021 --- Yes
OCS Air Permit application submitted (Applicant Action) --- 03-29-2022 --- Yes
OCS Air Permit application complete (Applicant Action) --- 06-29-2022 --- No
Issuance of final decision/permit approval (Agency Action) --- 06-29-2023 --- No