Permitting Action Modification History

Complete
MOA was executed early, on Oct 27, prior to the Oct 30 milestone. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 06-29-2021 06-29-2021 --- Yes
Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action) 06-29-2021 06-29-2021 --- Yes
Section 106 consultation concluded (Agency Action) 05-02-2023 10-27-2023 --- Yes
In Progress
The CVOW NEPA schedule shifted by four months in June 2022. The new 106 schedule reflects the current ROD date.. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 06-29-2021 06-29-2021 --- Yes
Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action) 06-29-2021 06-29-2021 --- Yes
Section 106 consultation concluded (Agency Action) 05-02-2023 10-30-2023 --- No