Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 07-02-2021 07-02-2021 --- Yes
Scoping (Agency Action) 07-19-2021 07-19-2021 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 08-01-2022 12-16-2022 --- Yes
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 05-01-2023 09-29-2023 --- Yes
Issuance of Lead Agency Record of Decision (Agency Action) 06-01-2023 10-30-2023 --- Yes
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 07-02-2021 07-02-2021 --- Yes
Scoping (Agency Action) 07-19-2021 07-19-2021 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 08-01-2022 12-16-2022 --- Yes
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 05-01-2023 09-29-2023 --- Yes
Issuance of Lead Agency Record of Decision (Agency Action) 06-01-2023 10-30-2023 --- No
In Progress
The delayed timing of submittal of information towards the Marine Mammal Protection Act (MMPA) permitting process by the project sponsor led to the need to revise the COP review and approval schedule for the CVOW Project.  The DEIS was shifted by 4-months with a new milestone date of 12/16/22.  The FEIS and ROD are being adjusted accordingly. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 07-02-2021 07-02-2021 --- Yes
Scoping (Agency Action) 07-19-2021 07-19-2021 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 08-01-2022 12-16-2022 --- Yes
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 05-01-2023 09-29-2023 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 06-01-2023 10-30-2023 --- No
In Progress
DEIS date changed from 8/1/22 to 12/16/22, due to the delayed submittal of information for the MMPA permitting process by the lessee, Dominion Energy Virginia, leading to the revision of the COP review and approval schedule. The initial MMPA permit application to NMFS has interdependencies on the ESA consultation process, including BOEM's preparation of the biological assessment, and finalizing the DEIS. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 07-02-2021 07-02-2021 --- Yes
Scoping (Agency Action) 07-19-2021 07-19-2021 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 08-01-2022 12-16-2022 --- Yes
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 05-01-2023 05-01-2023 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 06-01-2023 06-01-2023 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 07-02-2021 07-02-2021 --- Yes
Scoping (Agency Action) 07-19-2021 07-19-2021 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 08-01-2022 12-16-2022 --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 05-01-2023 05-01-2023 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 06-01-2023 06-01-2023 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 07-02-2021 07-02-2021 --- Yes
Scoping (Agency Action) 07-19-2021 07-19-2021 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 08-01-2022 08-01-2022 --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 05-01-2023 05-01-2023 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 06-01-2023 06-01-2023 --- No