USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

Planned
The timing of the OCS Air Permit is planned to cover the project construction activity, anticipated in late 2027 to early 2028. The proposed milestone for the OCS Air Permit has been shifted in accordance with the proposed schedule shift for the project.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 04-07-2023 05-15-2024 --- Yes
OCS Air Permit application submitted (Applicant Action) 04-08-2023 11-11-2025 --- No
OCS Air Permit application complete (Applicant Action) 05-22-2023 08-11-2026 --- No
Issuance of final decision/permit approval (Agency Action) 12-16-2024 08-11-2027 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 04-07-2023 09-29-2023 --- Yes
OCS Air Permit application submitted (Applicant Action) 04-08-2023 05-30-2024 --- No
OCS Air Permit application complete (Applicant Action) 05-22-2023 11-30-2024 --- No
Issuance of final decision/permit approval (Agency Action) 12-16-2024 01-02-2026 --- No
Planned
This new schedule accommodates the applicant's request to pursue the OCS air permit closer to the proposed time of construction.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 04-07-2023 09-30-2023 --- No
OCS Air Permit application submitted (Applicant Action) 04-08-2023 05-30-2024 --- No
OCS Air Permit application complete (Applicant Action) 05-22-2023 11-30-2024 --- No
Issuance of final decision/permit approval (Agency Action) 12-16-2024 01-02-2026 --- No
Planned
Original Target Date Entry Effort
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 04-07-2023 04-07-2023 --- No
OCS Air Permit application submitted (Applicant Action) 04-08-2023 04-08-2023 --- No
OCS Air Permit application complete (Applicant Action) 05-22-2023 05-22-2023 --- No
Issuance of final decision/permit approval (Agency Action) 12-16-2024 12-16-2024 --- No