Permitting Action Modification History

Complete
The milestone was completed four days ahead of schedule.   , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ITA Application Submitted (Applicant Action) 02-16-2022 02-16-2022 --- Yes
NOAA Determines ITA Application is Complete (Applicant Action) 04-01-2022 08-12-2022 --- Yes
Publish Notice of Receipt in Federal Register (LOA Only) (Agency Action) 05-04-2022 09-15-2022 --- Yes
Publish Proposed ITA in Federal Register (Agency Action) 08-31-2022 05-04-2023 --- Yes
Publish Final ITA Regulations in Federal Register (LOA Only) (Agency Action) 08-18-2023 01-23-2024 --- Yes
ITA decision rendered (Agency Action) 04-03-2023 02-01-2024 --- Yes
In Progress
Milestone for 'Publish Final ITA Regulations' was met eight days early on Jan 23 (earlier than the posted milestone of Jan 31, 2024). , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ITA Application Submitted (Applicant Action) 02-16-2022 02-16-2022 --- Yes
NOAA Determines ITA Application is Complete (Applicant Action) 04-01-2022 08-12-2022 --- Yes
Publish Notice of Receipt in Federal Register (LOA Only) (Agency Action) 05-04-2022 09-15-2022 --- Yes
Publish Proposed ITA in Federal Register (Agency Action) 08-31-2022 05-04-2023 --- Yes
Publish Final ITA Regulations in Federal Register (LOA Only) (Agency Action) 08-18-2023 01-23-2024 --- Yes
ITA decision rendered (Agency Action) 04-03-2023 02-05-2024 --- No
In Progress
The project sponsor's night time pile driving request delayed final rule production, which will delay publication of the final rule. NMFS is not proposing extending the ITA decision milestone at this time.  This was discussed with the project sponsor and there was agreement.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ITA Application Submitted (Applicant Action) 02-16-2022 02-16-2022 --- Yes
NOAA Determines ITA Application is Complete (Applicant Action) 04-01-2022 08-12-2022 --- Yes
Publish Notice of Receipt in Federal Register (LOA Only) (Agency Action) 05-04-2022 09-15-2022 --- Yes
Publish Proposed ITA in Federal Register (Agency Action) 08-31-2022 05-04-2023 --- Yes
Publish Final ITA Regulations in Federal Register (LOA Only) (Agency Action) 08-18-2023 01-31-2024 --- No
ITA decision rendered (Agency Action) 04-03-2023 02-05-2024 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ITA Application Submitted (Applicant Action) 02-16-2022 02-16-2022 --- Yes
NOAA Determines ITA Application is Complete (Applicant Action) 04-01-2022 08-12-2022 --- Yes
Publish Notice of Receipt in Federal Register (LOA Only) (Agency Action) 05-04-2022 09-15-2022 --- Yes
Publish Proposed ITA in Federal Register (Agency Action) 08-31-2022 05-04-2023 --- Yes
Publish Final ITA Regulations in Federal Register (LOA Only) (Agency Action) 08-18-2023 01-05-2024 --- No
ITA decision rendered (Agency Action) 04-03-2023 02-05-2024 --- No
In Progress
The MMPA milestone for publication of the proposed rule was extended to allow time for the applicant to provide new project information to be incorporated into the proposed rule.  The final two MMPA milestones were corrected, and were actually moved sooner than the previous published target dates, due to an error in the previous dates.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ITA Application Submitted (Applicant Action) 02-16-2022 02-16-2022 --- Yes
NOAA Determines ITA Application is Complete (Applicant Action) 04-01-2022 08-12-2022 --- Yes
Publish Notice of Receipt in Federal Register (LOA Only) (Agency Action) 05-04-2022 09-15-2022 --- Yes
Publish Proposed ITA in Federal Register (Agency Action) 08-31-2022 05-04-2023 --- No
Publish Final ITA Regulations in Federal Register (LOA Only) (Agency Action) 08-18-2023 01-05-2024 --- No
ITA decision rendered (Agency Action) 04-03-2023 02-05-2024 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ITA Application Submitted (Applicant Action) 02-16-2022 02-16-2022 --- Yes
NOAA Determines ITA Application is Complete (Applicant Action) 04-01-2022 08-12-2022 --- Yes
Publish Notice of Receipt in Federal Register (LOA Only) (Agency Action) 05-04-2022 09-15-2022 --- Yes
Publish Proposed ITA in Federal Register (Agency Action) 08-31-2022 04-17-2023 --- No
Publish Final ITA Regulations in Federal Register (LOA Only) (Agency Action) 08-18-2023 02-02-2024 --- No
ITA decision rendered (Agency Action) 04-03-2023 03-04-2024 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ITA Application Submitted (Applicant Action) 02-16-2022 02-16-2022 --- Yes
NOAA Determines ITA Application is Complete (Applicant Action) 04-01-2022 08-12-2022 --- Yes
Publish Notice of Receipt in Federal Register (LOA Only) (Agency Action) 05-04-2022 09-15-2022 --- No
Publish Proposed ITA in Federal Register (Agency Action) 08-31-2022 04-17-2023 --- No
Publish Final ITA Regulations in Federal Register (LOA Only) (Agency Action) 08-18-2023 02-02-2024 --- No
ITA decision rendered (Agency Action) 04-03-2023 03-04-2024 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOAA Determines ITA Application is Complete (Applicant Action) --- 08-16-2022 --- No
Publish Notice of Receipt in Federal Register (LOA Only) (Agency Action) --- 09-15-2022 --- No
Publish Proposed ITA in Federal Register (Agency Action) --- 04-17-2023 --- No
Publish Final ITA Regulations in Federal Register (LOA Only) (Agency Action) --- 02-02-2024 --- No
ITA decision rendered (Agency Action) --- 03-04-2024 --- No