Permitting Action Modification History

Cancelled
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ITA Application Submitted (Applicant Action) 06-19-2023 06-19-2023 06-12-2023 Yes
NOAA Determines ITA Application is Complete (Applicant Action) 05-02-2022 11-14-2022 02-14-2025 No
Publish Notice of Receipt in Federal Register (LOA Only) (Agency Action) 04-15-2022 12-13-2022 03-17-2025 No
Publish Proposed ITA in Federal Register (Agency Action) 11-14-2022 07-14-2023 10-21-2025 No
Publish Final ITA Regulations in Federal Register (LOA Only) (Agency Action) 10-03-2023 03-29-2024 07-17-2026 No
ITA decision rendered (Agency Action) 11-03-2023 04-29-2024 08-17-2026 No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ITA Application Submitted (Applicant Action) 06-19-2023 06-19-2023 06-12-2023 Yes
NOAA Determines ITA Application is Complete (Applicant Action) 05-02-2022 11-14-2022 02-14-2025 No
Publish Notice of Receipt in Federal Register (LOA Only) (Agency Action) 04-15-2022 12-13-2022 03-17-2025 No
Publish Proposed ITA in Federal Register (Agency Action) 11-14-2022 07-14-2023 10-21-2025 No
Publish Final ITA Regulations in Federal Register (LOA Only) (Agency Action) 10-03-2023 03-29-2024 07-17-2026 No
ITA decision rendered (Agency Action) 11-03-2023 04-29-2024 08-17-2026 No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ITA Application Submitted (Applicant Action) 06-19-2023 06-19-2023 06-12-2023 Yes
NOAA Determines ITA Application is Complete (Applicant Action) 05-02-2022 11-14-2022 12-11-2023 No
Publish Notice of Receipt in Federal Register (LOA Only) (Agency Action) 04-15-2022 12-13-2022 01-09-2024 No
Publish Proposed ITA in Federal Register (Agency Action) 11-14-2022 07-14-2023 08-09-2024 No
Publish Final ITA Regulations in Federal Register (LOA Only) (Agency Action) 10-03-2023 03-29-2024 05-02-2025 No
ITA decision rendered (Agency Action) 11-03-2023 04-29-2024 06-02-2025 No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ITA Application Submitted (Applicant Action) 06-19-2023 06-19-2023 06-12-2023 No
NOAA Determines ITA Application is Complete (Applicant Action) 05-02-2022 11-14-2022 12-11-2023 No
Publish Notice of Receipt in Federal Register (LOA Only) (Agency Action) 04-15-2022 12-13-2022 01-09-2024 No
Publish Proposed ITA in Federal Register (Agency Action) 11-14-2022 07-14-2023 08-09-2024 No
Publish Final ITA Regulations in Federal Register (LOA Only) (Agency Action) 10-03-2023 03-29-2024 05-02-2025 No
ITA decision rendered (Agency Action) 11-03-2023 04-29-2024 06-02-2025 No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ITA Application Submitted (Applicant Action) 06-19-2023 06-19-2023 --- No
NOAA Determines ITA Application is Complete (Applicant Action) 05-02-2022 11-14-2022 12-11-2023 No
Publish Notice of Receipt in Federal Register (LOA Only) (Agency Action) 04-15-2022 12-13-2022 01-09-2024 No
Publish Proposed ITA in Federal Register (Agency Action) 11-14-2022 07-14-2023 08-09-2024 No
Publish Final ITA Regulations in Federal Register (LOA Only) (Agency Action) 10-03-2023 03-29-2024 05-02-2025 No
ITA decision rendered (Agency Action) 11-03-2023 04-29-2024 06-02-2025 No
Planned
The applicant informed NOAA/NMFS staff that their submission of the MMPA incidental take authorization application would be delayed later than previously scheduled.  Due to this delay, the entire MMPA process is delayed accordingly.  This delay also affects the ESA/EFH milestones due to dependencies between ESA and MMPA milestones, and dependencies between ESA and EFH milestones.  This applicant delay also affects BOEM's EIS schedule, which necessitates revision of our action's milestones due to relationships/dependencies between our action milestones and EIS milestones.   , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ITA Application Submitted (Applicant Action) 06-19-2023 06-19-2023 --- No
NOAA Determines ITA Application is Complete (Applicant Action) 05-02-2022 11-14-2022 12-09-2023 No
Publish Notice of Receipt in Federal Register (LOA Only) (Agency Action) 04-15-2022 12-13-2022 01-09-2024 No
Publish Proposed ITA in Federal Register (Agency Action) 11-14-2022 07-14-2023 08-09-2024 No
Publish Final ITA Regulations in Federal Register (LOA Only) (Agency Action) 10-03-2023 03-29-2024 05-02-2025 No
ITA decision rendered (Agency Action) 11-03-2023 04-29-2024 06-02-2025 No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ITA Application Submitted (Applicant Action) --- --- --- No
NOAA Determines ITA Application is Complete (Applicant Action) 11-14-2022 11-14-2022 --- No
Publish Notice of Receipt in Federal Register (LOA Only) (Agency Action) 12-13-2022 12-13-2022 --- No
Publish Proposed ITA in Federal Register (Agency Action) 07-14-2023 07-14-2023 --- No
Publish Final ITA Regulations in Federal Register (LOA Only) (Agency Action) 03-29-2024 03-29-2024 --- No
ITA decision rendered (Agency Action) 04-29-2024 04-29-2024 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOAA Determines ITA Application is Complete (Applicant Action) --- 09-14-2022 --- No
Publish Notice of Receipt in Federal Register (LOA Only) (Agency Action) --- 10-13-2022 --- No
Publish Proposed ITA in Federal Register (Agency Action) --- 05-15-2023 --- No
Publish Final ITA Regulations in Federal Register (LOA Only) (Agency Action) --- 01-12-2024 --- No
ITA decision rendered (Agency Action) --- 02-12-2024 --- No