Permitting Action Modification History

Cancelled
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 07-02-2022 03-03-2023 03-06-2025 No
NOAA determines EFH Assessment is Complete (Agency Action) 11-14-2022 06-29-2023 10-21-2025 No
NOAA Issues any EFH Conservation Recommendations (Agency Action) 01-13-2023 08-28-2023 12-22-2025 No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 07-02-2022 03-03-2023 03-06-2025 No
NOAA determines EFH Assessment is Complete (Agency Action) 11-14-2022 06-29-2023 10-21-2025 No
NOAA Issues any EFH Conservation Recommendations (Agency Action) 01-13-2023 08-28-2023 12-22-2025 No
Planned
The applicant informed NOAA/NMFS staff that their submission of the MMPA incidental take authorization application would be delayed 10 months later than previously scheduled.  Due to this delay, the entire MMPA process is delayed by 10 months.  This delay also affects the ESA/EFH milestones due to dependencies between ESA and MMPA milestones, and dependencies between ESA and EFH milestones.  This applicant delay also affects BOEM's EIS schedule, which is in process of being revised per dependencies with EIS milestones and milestones associated with our actions.   , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 07-02-2022 03-03-2023 12-13-2023 No
NOAA determines EFH Assessment is Complete (Agency Action) 11-14-2022 06-29-2023 07-10-2024 No
NOAA Issues any EFH Conservation Recommendations (Agency Action) 01-13-2023 08-28-2023 10-08-2024 No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 03-03-2023 03-03-2023 --- No
NOAA determines EFH Assessment is Complete (Agency Action) 06-29-2023 06-29-2023 --- No
NOAA Issues any EFH Conservation Recommendations (Agency Action) 08-28-2023 08-28-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) --- 12-16-2022 --- No
NOAA determines EFH Assessment is Complete (Agency Action) --- 04-13-2023 --- No
NOAA Issues any EFH Conservation Recommendations (Agency Action) --- 06-13-2023 --- No