Permitting Action Modification History

Cancelled
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 10-03-2022 10-03-2022 07-11-2025 No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 11-14-2022 11-14-2022 10-10-2025 No
ESA Consultation Concludes (Agency Action) 06-12-2023 06-12-2023 03-11-2026 No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 10-03-2022 10-03-2022 07-11-2025 No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 11-14-2022 11-14-2022 10-10-2025 No
ESA Consultation Concludes (Agency Action) 06-12-2023 06-12-2023 03-11-2026 No
Planned
The Milestones are being updated to align with initial MMPA permit submittal. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 10-03-2022 10-03-2022 04-26-2024 No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 11-14-2022 11-14-2022 07-10-2024 No
ESA Consultation Concludes (Agency Action) 06-12-2023 06-12-2023 11-18-2024 No
Planned
Original Target Date Data Entry Effort , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 10-03-2022 10-03-2022 --- No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 11-14-2022 11-14-2022 --- No
ESA Consultation Concludes (Agency Action) 06-12-2023 06-12-2023 --- No