Permitting Action Modification History

Cancelled
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 07-02-2022 03-03-2023 03-06-2025 No
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 11-14-2022 06-29-2023 10-21-2025 No
ESA Consultation Concludes (Agency Action) 05-03-2023 11-27-2023 03-20-2026 No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 07-02-2022 03-03-2023 03-06-2025 No
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 11-14-2022 06-29-2023 10-21-2025 No
ESA Consultation Concludes (Agency Action) 05-03-2023 11-27-2023 03-20-2026 No
Planned
The applicant informed NOAA/NMFS staff that their submission of the MMPA incidental take authorization application would be delayed later than previously scheduled.  Due to this delay, the entire MMPA process is delayed.  This delay also affects the ESA/EFH milestones due to dependencies between ESA and MMPA milestones, and dependencies between ESA and EFH milestones.  This applicant delay also affects BOEM's EIS schedule, which necessitates revision of our milestones due to relationships between EIS milestones and our action milestones.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 07-02-2022 03-03-2023 12-13-2023 No
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 11-14-2022 06-29-2023 07-10-2024 No
ESA Consultation Concludes (Agency Action) 05-03-2023 11-27-2023 12-06-2024 No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 03-03-2023 03-03-2023 --- No
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 06-29-2023 06-29-2023 --- No
ESA Consultation Concludes (Agency Action) 11-27-2023 11-27-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) --- 12-16-2022 --- No
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) --- 04-13-2023 --- No
ESA Consultation Concludes (Agency Action) --- 09-11-2023 --- No