Permitting Action Modification History

Complete
Permit decision rendered ahead of schedule.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 07-03-2022 05-17-2022 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 07-17-2022 08-31-2022 --- Yes
Publication of Public Notice (Agency Action) 08-01-2022 09-15-2022 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 08-31-2023 01-25-2024 --- Yes
In Progress
The final milestone has been adjusted in accordance with BOEM's revised schedule, to allow the 90 day decision making timeframe from BOEM ROD to USACE permit decision. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 07-03-2022 05-17-2022 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 07-17-2022 08-31-2022 --- Yes
Publication of Public Notice (Agency Action) 08-01-2022 09-15-2022 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 08-31-2023 01-29-2024 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 07-03-2022 05-17-2022 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 07-17-2022 08-31-2022 --- Yes
Publication of Public Notice (Agency Action) 08-01-2022 09-15-2022 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 08-31-2023 08-30-2023 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 07-03-2022 05-17-2022 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 07-17-2022 08-31-2022 --- Yes
Publication of Public Notice (Agency Action) 08-01-2022 09-15-2022 --- No
Final Verification/Permit Decision Rendered (Agency Action) 08-31-2023 08-30-2023 --- No
Planned
Applicant requires additional time to complete a wetland delineation and modify the application to reflect the revised impacts.  Public notice date revised based on updated application submittal date.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 07-03-2022 05-17-2022 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 07-17-2022 08-31-2022 --- No
Publication of Public Notice (Agency Action) 08-01-2022 09-15-2022 --- No
Final Verification/Permit Decision Rendered (Agency Action) 08-31-2023 08-30-2023 --- No
Planned
The date change is based on the applicant's schedule. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 07-03-2022 05-17-2022 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 07-17-2022 08-17-2022 --- No
Publication of Public Notice (Agency Action) 08-01-2022 09-01-2022 --- No
Final Verification/Permit Decision Rendered (Agency Action) 08-31-2023 08-30-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 05-17-2022 05-17-2022 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 07-17-2022 08-15-2022 --- No
Publication of Public Notice (Agency Action) 08-01-2022 08-30-2022 --- No
Final Verification/Permit Decision Rendered (Agency Action) 08-31-2023 08-31-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 05-17-2022 05-17-2022 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 07-17-2022 07-17-2022 --- No
Publication of Public Notice (Agency Action) 08-01-2022 08-01-2022 --- No
Final Verification/Permit Decision Rendered (Agency Action) 08-31-2023 08-31-2023 --- No