Permitting Action Modification History

Complete
Permit decision rendered ahead of schedule. 
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 07-03-2022 05-17-2022 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 07-17-2022 08-31-2022 --- Yes
Publication of Public Notice (Agency Action) 08-01-2022 09-15-2022 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 08-31-2023 01-25-2024 --- Yes
In Progress
The final milestone has been adjusted in accordance with BOEM's revised schedule, to allow the 90 day decision making timeframe from BOEM ROD to USACE permit decision.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 07-03-2022 05-17-2022 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 07-17-2022 08-31-2022 --- Yes
Publication of Public Notice (Agency Action) 08-01-2022 09-15-2022 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 08-31-2023 01-29-2024 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 07-03-2022 05-17-2022 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 07-17-2022 08-31-2022 --- Yes
Publication of Public Notice (Agency Action) 08-01-2022 09-15-2022 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 08-31-2023 08-30-2023 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 07-03-2022 05-17-2022 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 07-17-2022 08-31-2022 --- Yes
Publication of Public Notice (Agency Action) 08-01-2022 09-15-2022 --- No
Final Verification/Permit Decision Rendered (Agency Action) 08-31-2023 08-30-2023 --- No
Planned
Applicant requires additional time to complete a wetland delineation and modify the application to reflect the revised impacts.  Public notice date revised based on updated application submittal date. 
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 07-03-2022 05-17-2022 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 07-17-2022 08-31-2022 --- No
Publication of Public Notice (Agency Action) 08-01-2022 09-15-2022 --- No
Final Verification/Permit Decision Rendered (Agency Action) 08-31-2023 08-30-2023 --- No
Planned
The date change is based on the applicant's schedule.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 07-03-2022 05-17-2022 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 07-17-2022 08-17-2022 --- No
Publication of Public Notice (Agency Action) 08-01-2022 09-01-2022 --- No
Final Verification/Permit Decision Rendered (Agency Action) 08-31-2023 08-30-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 05-17-2022 05-17-2022 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 07-17-2022 08-15-2022 --- No
Publication of Public Notice (Agency Action) 08-01-2022 08-30-2022 --- No
Final Verification/Permit Decision Rendered (Agency Action) 08-31-2023 08-31-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 05-17-2022 05-17-2022 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 07-17-2022 07-17-2022 --- No
Publication of Public Notice (Agency Action) 08-01-2022 08-01-2022 --- No
Final Verification/Permit Decision Rendered (Agency Action) 08-31-2023 08-31-2023 --- No