Permitting Action Modification History
Modifications on 10/25/2023
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) | 10-05-2020 | 10-05-2020 | --- | Yes |
| Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) | 01-19-2021 | 01-19-2021 | --- | Yes |
| Publication of Public Notice (Agency Action) | 05-11-2021 | 04-30-2022 | --- | No |
| Final Verification/Permit Decision Rendered (Agency Action) | 05-30-2022 | 05-30-2022 | --- | No |
Modifications on 04/12/2022
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) | 10-05-2020 | 10-05-2020 | --- | Yes |
| Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) | 01-19-2021 | 01-19-2021 | --- | Yes |
| Publication of Public Notice (Agency Action) | 05-11-2021 | 04-30-2022 | --- | No |
| Final Verification/Permit Decision Rendered (Agency Action) | 05-30-2022 | 05-30-2022 | --- | No |